Building and Tracking a Budget

20 min read Training Guide

Build a yearly budget for a unit or department from volume and rates, spread it across the months, track spending before the P&L arrives, and reforecast when plans change.

Table of contents

A budget is your plan for the year written in dollars: how much you expect to sell or handle, and what you expect to spend to do it. Once it is approved, every monthly P&L is measured against it, and so are you. A budget built from real drivers is one you can hit and defend. A budget built from last year plus a guess is one you will spend all year explaining.

This works the same way for a store, a restaurant, a warehouse, a clinic, a service department or an office. A unit with no sales line, such as an office or a maintenance shop, builds a budget that is all costs. The steps do not change.

What You Will Be Able to Do

  • Gather what you need before you build: history, known changes and the company's assumptions.
  • Build each line from a driver, such as volume times a rate.
  • Spread a yearly number across the months using your own seasonal pattern.
  • Track spending during the month so the P&L holds no surprises.
  • Reforecast the rest of the year, and ask for a change with numbers behind it.

Fixed, Variable and In Between

Every cost behaves in one of three ways. How it behaves decides how you budget it.

Kind Moves with volume? Examples
Fixed No Rent, salaries, a monthly service contract, software subscriptions
Variable Yes, about in step Goods sold, packaging, shipping, card processing fees
Semi-variable Partly Hourly labor, utilities, supplies, repairs

Fixed costs come from contracts and schedules. Variable costs come from volume times a rate. Semi-variable costs need both: a base amount plus a part that moves.

There are also two kinds of budget. The operating budget covers sales and the costs of running the unit each month. The capital budget covers equipment and improvements that last for years, such as a new machine, a vehicle or a remodel. Your company sets the dollar amount above which a purchase counts as capital. Capital items reach your P&L slowly, through depreciation. Ask accounting for the threshold so you put each purchase in the right budget.

Before You Start

Gather these before you open the budget template:

  1. History. At least 12 months of actuals by line and by month, and 24 or 36 if you have them.
  2. One-time items. Mark anything that will not happen again: a big repair, a closing day, a startup cost, a storm.
  3. Known changes. New contract prices, a lease increase, a planned remodel, a new service, a position added or cut.
  4. Company assumptions. Finance usually sets the planned wage increase, the rate for payroll taxes and benefits, and a sales or volume target. Use theirs, not your own.
  5. The template and the deadline. Most companies have a budget form and a calendar. Ask for both early.

Build Each Line From a Driver

A driver is the thing that causes a cost. Most lines can be written as a driver times a rate.

Line Driver Rate
Sales Orders, visits, jobs or units Average sale per order or job
Goods and supplies Orders or units Cost per order or unit
Hourly labor Hours, from expected volume Average wage
Payroll taxes and benefits Wages The rate accounting gives you
Contracts Months Contract price, with any scheduled increase
Repairs Normal yearly amount History, without one-time items

Labor usually comes from a weekly labor plan and the company's staffing model. Whatever hours you plan, add payroll taxes and benefits on top. If accounting tells you that taxes and benefits run 20 percent of wages, $300,000 of wages needs another $60,000.

Worked Example: A Year for One Unit

Last year the unit handled 48,000 orders at an average of $25.00, for $1,200,000 in sales. Supplies cost $30,000. Here is how next year's lines are built.

Sales. The company expects 5 percent more orders and no price change.

  1. Orders: 48,000 x 1.05 = 50,400.
  2. Sales: 50,400 x $25.00 = $1,260,000.

Supplies. Supplies follow orders.

  1. Last year's cost per order: $30,000 / 48,000 = $0.625.
  2. The supplier has announced a 4 percent price increase: $0.625 x 1.04 = $0.65.
  3. Budget: 50,400 x $0.65 = $32,760.

Cleaning contract. The contract is $1,800 a month, with a 3 percent increase on July 1.

  1. January to June: 6 x $1,800 = $10,800.
  2. July to December: $1,800 x 1.03 = $1,854, and 6 x $1,854 = $11,124.
  3. Budget: $10,800 + $11,124 = $21,924.

Repairs. The last three years were $9,500, $14,800 and $10,100. The $14,800 year included a one-time $5,000 roof repair.

  1. Take out the one-time item: $14,800 - $5,000 = $9,800.
  2. Average the three normal years: ($9,500 + $9,800 + $10,100) / 3 = $9,800.
  3. Budget $9,800, or a little more if equipment is aging and you can say why.

If you had simply added a few percent to last year's supplies, you would have missed both the extra orders and the price increase. If you had averaged repairs with the roof job left in, you would have padded the line by more than $1,600.

Spread the Year Across the Months

A yearly total is not enough. Your P&L comes monthly, so the budget has to say what each month should look like. Spreading it evenly, one twelfth a month, makes every busy month look over budget and every slow month look under.

Use your own pattern. Here is last year's sales by quarter:

Quarter Last year Share Next year's budget
1 $264,000 22% $277,200
2 $312,000 26% $327,600
3 $324,000 27% $340,200
4 $300,000 25% $315,000
Year $1,200,000 100% $1,260,000

Each share is that quarter's sales divided by the year: $264,000 / $1,200,000 = 22 percent. Do the same by month. If March was 7.5 percent of last year's sales, March's budget is $1,260,000 x 7.5% = $94,500. Use two or three years of history if one year had something unusual in it.

Then spread each cost by how it behaves:

  • Variable costs follow sales or volume. March's orders are 50,400 x 7.5% = 3,780, so March's supplies are 3,780 x $0.65 = $2,457.
  • Fixed costs follow the contract or the schedule: the same amount each month, with any increase in the month it starts.
  • Seasonal and once-a-year costs go in the month they happen: an annual license, a yearly service visit, holiday staffing, snow removal.

Watch the calendar too. A month with an extra weekend, or a holiday that moves from one month to another, shifts both sales and labor.

Check It Before You Send It

  1. Compare each cost as a percent of sales with last year. Be ready to explain any line that moves.
  2. Read the total against the company's target. If it falls short, do not change numbers until it fits. Show what it would take to get there, and let your manager decide.
  3. Do not pad. A line built high to give you room hides real problems and costs you trust when someone finds it.
  4. Write a short note for each big line on how you built it. You will need it in six months when someone asks.

Track Spending During the Month

The monthly P&L usually arrives after the month closes, sometimes weeks later. By then it is too late to change that month. Keep your own running log during the month.

Date Vendor and PO Line Amount
3rd Supply order, PO 2211 Supplies $640
10th Supply order, PO 2230 Supplies $690
17th Supply order, PO 2244 Supplies $650

Log purchases when you order them, not when the bill is paid. A commitment is money you have promised through an order, even though no invoice has arrived yet. Ask accounting whether goods received in one month but billed in the next are booked to the month they arrived (called an accrual). That tells you which month a cost will land in.

Worked Example: The Midmonth Check

March's supplies budget is $2,457. By the 18th of the 31-day month, the log shows $1,980 ordered, all normal weekly orders.

  1. Daily pace: $1,980 / 18 = $110.
  2. Projected month: $110 x 31 = $3,410.
  3. Projected overrun: $3,410 - $2,457 = $953.

Before you react, check the cause. Were orders up this month? Did a price change? Is something being wasted, or being stolen? Then act while there are still 13 days left: hold orders that can wait, fix the cause, and tell your manager now. A warning on the 18th is far better than a surprise on the P&L.

If a single large order is in the log, such as a three-month supply bought at once, take it out before you figure the pace, or the projection will run high.

Reforecast When Things Change

A forecast is your best current guess at how the year will end. Many companies ask for one every month or every quarter. The budget stays the same, so you can still compare to the plan.

Full-year forecast = actual year to date + forecast for the months left.

Worked example. Repairs are budgeted at $9,800 for the year, or about $817 a month. At the end of June, actual repairs are $7,400, because of two large unplanned repairs. You expect the rest of the year to run normally.

  1. Forecast for July to December: 6 x $817 = $4,902.
  2. Full-year forecast: $7,400 + $4,902 = $12,302.
  3. Expected overrun: $12,302 - $9,800 = $2,502.

Tell your manager now, and bring options: costs you can hold elsewhere, or a request to cover it.

Ask for Money With Numbers

When you need something the budget did not include, write a short request:

  1. What: the item or change, and its cost.
  2. Why: the problem it solves.
  3. The numbers: what it saves or earns, and how fast it pays for itself.
  4. Options: at least one other way, including doing nothing, and what that costs.

Payback is the cost divided by what it saves each month. Say you rent a floor scrubber for $300 a month. Buying one costs $4,200, plus about $20 a month in parts. It saves $300 - $20 = $280 a month, so it pays for itself in $4,200 / $280 = 15 months. A purchase like this usually goes through the capital budget, so follow your company's process.

Common Mistakes

Mistake What it costs
Last year plus a percent Misses volume changes, price increases and one-time items
Forgetting payroll taxes and benefits Labor runs over every month
Spreading the year evenly Busy months look bad, slow months look good
Missing a contract increase A line that runs over from the month it starts
Waiting for the P&L to see spending No time left to fix the month
Spending what is left at year end Money wasted, and next year's budget cut
Padding lines Lost trust when found, and real problems hidden

Check Your Understanding

1. Last year's supplies were $18,000 on 36,000 orders. You expect 40,000 orders and a 5 percent price increase. What do you budget?

Cost per order is $18,000 / 36,000 = $0.50. With the increase, $0.50 x 1.05 = $0.525. Budget 40,000 x $0.525 = $21,000.

2. Repairs were $9,600, $10,400 and $16,000 over three years, and the $16,000 year included a one-time $6,000 replacement. What is a fair repair budget?

Take out the one-time item, leaving $10,000. Then average: ($9,600 + $10,400 + $10,000) / 3 = $10,000.

3. Your yearly sales budget is $900,000, and last December was 12 percent of last year's sales. What is December's budget, and why not $75,000?

$900,000 x 12% = $108,000. One twelfth, $75,000, would ignore that December is a busy month for this unit.

4. On the 15th of a 30-day month, you have ordered $2,100 of a $3,000 supply budget, all in normal weekly orders. What do you expect, and what do you do?

Pace is $2,100 / 15 = $140 a day, so the month is heading for $140 x 30 = $4,200, or $1,200 over. Find the cause, hold what can wait, and tell your manager now.

5. At the end of September, repairs are $9,000 against a full-year budget of $10,000. You expect about $800 a month for the rest of the year. What is your forecast?

$9,000 + (3 x $800) = $11,400, which is $1,400 over budget.

Key Takeaways

  • Build each line from a driver times a rate, not from last year plus a guess.
  • Take one-time items out of history, and add known changes such as contract increases.
  • Add payroll taxes and benefits to every dollar of planned wages.
  • Spread the year by your own seasonal pattern, and put once-a-year costs in the month they happen.
  • Track orders as you place them, and check your pace midmonth.
  • Reforecast as year to date plus the months left, and raise problems early with options.