Office Management

Coordinating Office Facilities and Equipment

20 min read Training Guide

Find out who fixes what under the lease, get repairs done fast, lay out desks safely, plan an office move, track equipment and its contracts, and work with IT on new hires and departures.

Table of contents

The office manager is usually the person everyone calls when something in the building breaks, a desk needs to move, a new hire needs a laptop, or the lease is coming up for renewal. You are rarely the one who fixes it. Your job is to know who is responsible, get the right person moving, keep the space safe while you wait, and keep records so the same problem does not cost twice. Most of that comes down to reading the lease, keeping good lists, and making clear requests.

What You Will Be Able to Do

  • Read the parts of an office lease that decide who pays for repairs and when notices are due
  • Report a repair so it gets fixed the first time, and judge how urgent it is
  • Arrange desks and storage so exits, panels and sprinklers stay clear
  • Plan a desk move or an office move, including everyone who needs the new address
  • Track equipment and its leases, and handle new-hire setups and departures with IT

Find Out Who Is Responsible

In a leased office, the lease decides which repairs the landlord makes and which ones your company pays for. Read it, or ask the owner for a summary of the key terms, before the first thing breaks.

Item Often handled by Where to check
Roof, structure, main heating and cooling, elevators Landlord The lease
Shared lobbies, restrooms and parking Landlord, billed back through shared costs The lease
Lights, doors, carpet and paint inside your space Either one The lease
Furniture, phones, computers, copier Your company or the equipment's leasing company Your contracts

Every lease is different, so the lease governs, not this table. A few lease terms come up often:

Term What it means
Gross lease Rent covers most building costs
Net lease You pay rent plus a share of taxes, insurance or maintenance
Common area maintenance (CAM) Your share of the costs of shared spaces, often estimated monthly and settled once a year
Renewal option Your right to extend, if you give notice by a set date
Holdover Staying after the lease ends, often at a much higher rent
Alterations Changes to the space, which usually need the landlord's written consent

Worked example. The lease ends August 31, 2028. It says the renewal option must be exercised by written notice at least 9 months before the end date, delivered by certified mail to the landlord's address in the notice section. Counting back 9 months from August 31 gives November 30, 2027. Put a reminder on August 31, 2027, a year out, to start comparing options, and another on October 15, 2027, so the authorized signer has time to sign and mail the notice by the right method. A notice sent by email when the lease requires certified mail may not count.

Only people with signing authority sign a lease, give notice, or agree to an alteration. Your job is to track the dates and make sure the right person acts in time.

Getting Repairs Done

  1. Make it safe first. Block off a wet floor, take a broken chair out of use, and keep people away from anything electrical that is damaged. Do not touch it.
  2. Decide whose repair it is, using the lease and the ownership list.
  3. Submit it through the right channel, such as the property manager's online request system or the service vendor's line. Include the exact location, what is wrong, when it started, photos, how urgent it is, and how the technician gets in.
  4. Log it: the date, the ticket number, and who you talked to.
  5. Follow up when the promised response time passes. If you keep getting no answer, go to the property manager directly, with your log.
  6. Confirm the repair worked before you close it in your log.
Urgency Examples Response
Emergency Water coming in, power out, broken entry glass, a door that will not lock Call now, and stay until it is safe
Same day No heat or cooling on a very hot or cold day, the only restroom out of order Call, then follow up in writing
Routine A light out, a squeaky door, a stained ceiling tile Normal request

Warning: If anyone smells gas, get everyone out and call 911 or the gas utility from outside, well away from the building. Do not try to find the leak.

Leave electrical work, gas work, plumbing, and anything that touches walls, ceilings or structure to the building's maintenance staff or a licensed contractor. Do not stand on a chair or a desk to reach anything. Use a ladder, or ask maintenance.

Space and Seating

Keep a floor plan with every desk numbered, who sits there, and the phone extension. It makes moves, new hires and emergency headcounts much easier. If people share desks on different days, keep a booking calendar so two people do not show up for one desk.

When you arrange desks, files and storage, keep these clear:

  • Exit routes. OSHA requires exit routes to be free and unobstructed, with nothing placed in them even for a short time, and each exit access at least 28 inches wide at all points (29 CFR 1910.36 and 1910.37). Boxes stacked in a hallway for a week still count.
  • Main aisles. The 2010 ADA Standards set 36 inches as the minimum clear width of an accessible walking route, so keep main aisles at least that wide for wheelchairs and walkers.
  • Electrical panels. OSHA requires clear working space in front of electrical equipment: at least 30 inches wide, and at least 3 feet deep for the common 120-volt panels, more for higher voltages. That space may not be used for storage (29 CFR 1910.303).
  • Sprinklers. Keep stored material at least 18 inches below sprinkler heads (29 CFR 1910.159).
  • Extinguishers, exit signs and alarm pulls. Keep them in sight and within reach.

Plug power strips straight into a wall outlet. A UL-listed power strip is not meant to be plugged into another power strip or an extension cord, and OSHA does not allow extension cords as a substitute for permanent wiring. If people keep needing more outlets in one spot, ask the building about adding one.

If an employee asks for a different chair, desk or seat because of a medical condition, pass the request to HR. It may be a request for a reasonable accommodation, and HR decides it.

Planning a Move

A desk move takes an hour of planning: confirm the new seat, tell IT if the phone or network connection must move, update the floor plan, and move the person's things in labeled boxes.

A whole office move takes months. Here is one example of how the work can be spread out. Your dates depend on the lease, the movers and your IT provider.

When What happens
4 to 6 months out Confirm the move date and budget, ask your IT provider and internet company for their lead times, get moving quotes
3 months out Pick the mover, plan seating, order furniture, plan the internet and phone move
2 months out Clean out files using the retention schedule, book the freight elevators at both buildings
1 month out Label every desk and box with the new desk number, collect certificates of insurance from the mover for both buildings
Move week Pack, move, set up IT, test every desk's phone and connection
After Walk the old space with the landlord, return keys, photograph the empty space, close out utilities

A few rules keep moves out of trouble:

  • Files on legal hold do not get thrown out, even if the retention schedule says they are due. Check with your manager before anything is shredded.
  • Most buildings require the mover's certificate of insurance before the movers may use the loading dock or elevators. Ask both buildings what they need.
  • Ask early how long a new internet line takes. Business lines often take weeks, not days.

Then tell everyone who needs the new address: customers, vendors, the bank, insurers, payroll, the post office, state agencies, your website and online listings, and anything printed with the address. The owner or bookkeeper tells the IRS with Form 8822-B, the business change of address form.

Tracking Equipment

Keep an equipment list, sometimes called an asset list, with each item's tag or serial number, who has it, where it is, when it was bought or leased, and when the warranty or lease ends. Check it against what is really there once a year. Before you pay for a repair, check whether the item is still under warranty.

Leased equipment, such as a copier, a postage meter or a water cooler, comes with contract dates. The renewal, notice and return terms belong on the recurring calendar like any other contract.

Copiers need one extra step. Many digital copiers have a hard drive that stores images of what was copied, printed, scanned or faxed. The Federal Trade Commission advises businesses to ask the vendor how the drive will be overwritten or removed before a leased copier goes back, to make sure the contract covers it, and to let a skilled technician do it rather than pulling the drive yourself. Get the vendor's confirmation in writing.

Working With IT

Whether IT is one person down the hall or an outside provider, they work from requests. Clear requests get fixed faster.

  • One problem per request. Say who is affected, what happened, when it started, the exact error message, and a screenshot.
  • Say how many people it affects. The whole office being offline is a different request from one person's mouse.
  • Do not work around security. Never share your login, install software IT has not approved, or plug in a USB drive you found.

New hires. Send IT the request well before the start date: name, start date, role, the systems and shared folders the person needs, equipment, and a phone extension. The new hire's manager approves which systems the person gets. Ask your IT provider how much lead time they need, and put it on your calendar.

Departures. Set up the departure with HR and IT before the last day, or at the moment of a termination.

  1. IT turns off the person's accounts at the agreed time, often the end of the last day.
  2. You collect the laptop, phone, badge, keys and any company card, and check them off the equipment list.
  3. Change any shared door or alarm codes the person knew.
  4. Follow your employer's policy for forwarding the person's email and saving their files.

An account left open after someone leaves is one of the easiest ways into an office's systems, so do not let it wait until next week.

Common Mistakes

Mistake What it costs
Paying for a repair the lease puts on the landlord Money the company did not owe
Sending a lease notice by the wrong method A renewal option lost, or a lease that renews anyway
Boxes stored in a hallway or in front of the panel A blocked exit and an OSHA violation
Shredding files during a move without checking holds Destroyed records a court or auditor needed
Returning a copier without wiping its drive Private documents leaving the building
Leaving a departed employee's accounts open A security gap anyone could use

Check Your Understanding

1. The ceiling over the conference room has a new water stain, and it is getting bigger. Who do you call, and what do you send?

Move people and equipment out from under it, then call the property manager, since the roof and building systems are usually the landlord's under the lease. Follow up in writing with the location, when you noticed it, photos and how to get in, and log the ticket.

2. A lease ends June 30. It says renewal notice must be given at least 6 months before, by certified mail. What is the last day, and when should you set your reminders?

Counting back 6 months from June 30 gives December 30 of the year before. Set a reminder several months earlier to compare options, and another a few weeks before December 30 so the signer can mail it by certified mail in time.

3. A team wants to stack supply boxes along the hallway to the back exit until the storage room is cleaned out. What do you say?

No. Exit routes must stay free and unobstructed, even for a short time. Find another spot, and keep material at least 18 inches below sprinkler heads in the storage room.

4. An employee resigns and her last day is Friday. What should be set up before then?

Arrange with HR and IT to turn off her accounts at the end of Friday, collect her laptop, badge, keys and any company card, check them off the equipment list, and change any shared codes she knew.

Key Takeaways

  • The lease decides who fixes what and how notices are sent. Track its dates and the exact notice method.
  • Make it safe first, then report repairs with location, photos and urgency, and log every ticket.
  • Keep exit routes clear and at least 28 inches wide, main aisles 36 inches, 3 feet in front of electrical panels, and 18 inches under sprinklers.
  • Plan a move months ahead, check legal holds before shredding, and tell everyone the new address.
  • Keep an equipment list, wipe copier drives before return, and shut off accounts when people leave.