Remove an old vanity, check fixture clearances, cut the new cabinet for the drain and supplies, fasten it level to studs, and set the top and backsplash so water stays out.

Table of contents

A bathroom vanity is a base cabinet that lives with water. Everything about installing one comes back to that: holes in the right place so the pipes pass cleanly, a cabinet level enough that water drains from the sink and not toward the wall, and a top sealed so splashes cannot soak the particleboard underneath. It is one of the most common jobs for carpenters, remodelers and maintenance staff, and it is easy to do well.

This guide covers a freestanding vanity cabinet with a one-piece top, such as cultured marble or solid surface with a built-in sink, and the prep for stone or vessel tops. Moving or extending a drain, vent or supply line is plumbing work. Rewiring a light or outlet is electrical work. Both may need a licensed trade and a permit.

What You Will Be Able to Do

  • Remove an old vanity without damaging the plumbing or walls.
  • Check the new vanity against the toilet and the room's clearances.
  • Locate and cut holes for the drain and supply lines.
  • Set the vanity level and fasten it to studs.
  • Set the top and backsplash, seal them, and leak-test the connections.

Removing the Old Vanity

  1. Shut off the water at the two stop valves under the sink. Open the faucet to prove they hold. If a stop will not shut off, close the main or the branch valve and have the stop replaced before you go on.
  2. Put a bucket and towels under the trap.
  3. Disconnect the supply lines from the stops and the faucet.
  4. Remove the trap at its slip nuts. Stuff a rag in the drain stub, so sewer gas and small parts stay out of the pipe.
  5. Cut the sealant between the top and the wall with a utility knife, and between the backsplash and the wall.
  6. Lift off the top. One-piece tops are heavy and can crack if lifted from one end. Use two people.
  7. Remove the screws through the cabinet back into the wall, and slide the cabinet out.
  8. Look at what was hidden. Check the floor and the wall behind for soft spots, stains, mold and rot. Water damage found now gets fixed now, before a new cabinet covers it.

Warning: In a building built before 1978, painted walls and trim may contain lead. Removing a vanity can disturb the paint around it, so follow lead-safe practices if the work disturbs more than a small painted area.

Check the Space

Fixture Clearances

The International Residential Code sets minimum clearances around toilets and sinks.

  • At least 15 inches from the center of the toilet to any side wall, partition or vanity.
  • At least 21 inches of clear space in front of the toilet and in front of the sink, to any wall, fixture or door.

A wider vanity than the old one can crowd the toilet below the 15-inch minimum. Measure before you order. Local codes and the adopted edition win, and accessible bathrooms have their own, larger clearances.

Worked Example: Will a Wider Vanity Fit?

The toilet's centerline is 39 inches from the left wall. The old 24-inch vanity sits against the left wall. The owner wants a 30-inch vanity in the same spot.

  • With the old vanity: 39 - 24 = 15 inches from the vanity side to the toilet's center. That just meets the minimum.
  • With a 30-inch vanity: 39 - 30 = 9 inches. That fails.

The new vanity cannot be wider than 24 inches here unless the toilet moves, and moving a toilet is a plumbing job.

Other Checks

  • Door swing. The vanity doors and the bathroom door must both open.
  • Height. Vanities come in several heights. A taller one may put the drain opening in the sink lower relative to the wall stub, so check that the trap can still connect with the trap arm sloping down toward the wall.
  • Outlets and lights. The outlet near the sink must stay reachable, and the mirror and light must still center on the sink.

Mark the Layout

  1. Find and mark the studs behind the vanity.
  2. Draw the vanity's outline on the floor and the wall, using the actual cabinet.
  3. Mark its centerline. Center it on the drain if the plan does, or on the mirror and light.
  4. Check the floor for level along the front and the back. Note the high point.

Cut for the Plumbing

Most vanities have a back panel or a rail that must be cut for the drain and the supply stubs.

  1. Measure from the vanity's outline on the wall to the center of the drain stub and each supply stub, sideways.
  2. Measure from the floor up to the center of each stub.
  3. Transfer those numbers to the cabinet back, measured from the same side edge and the bottom edge.
  4. Cut each hole with a hole saw about 1/2 inch larger than the pipe, or cut one rectangular opening that clears all three with room to work. Keep enough of the back rail to fasten through.
  5. Slide the cabinet into place to test the fit. Adjust the holes before you fasten anything.

Worked Example: Supply Holes

The vanity will sit with its left side 6 inches from the left wall. The hot stub is 17 inches from the left wall, the cold stub 25 inches, and both are 21 inches above the floor.

  • Hot: 17 - 6 = 11 inches from the cabinet's left edge.
  • Cold: 25 - 6 = 19 inches from the cabinet's left edge.
  • Height: 21 inches up from the bottom of the cabinet back, if the cabinet sits right on the floor. If it will sit on a 1/4-inch shim, measure 20-3/4 inches up.

Set and Fasten the Cabinet

  1. Slide it in over the stubs, without bending or forcing a pipe.
  2. Level it side to side and front to back, and check that the face is plumb. Use composite shims, since wood shims rot if a leak soaks them.
  3. Shim behind the back rail at the studs if the wall is hollow, so screwing it tight does not rack the box.
  4. Fasten through the back rail into studs with cabinet screws, not drywall screws.
  5. Scribe a filler if the vanity meets a side wall and the plan calls for one.
  6. Trim the shims and cover them with the toe kick or base trim.

Wall-Hung Vanities

A vanity that hangs on the wall with no legs carries all its weight, plus anyone who leans on it, on its fasteners.

  • It needs solid blocking in the wall at the mounting height, or the bracket the maker supplies fastened into studs.
  • If the wall has no blocking, the drywall must be opened to add it. Do not hang a vanity on drywall anchors.
  • One cabinet maker calls for longer screws, 3-1/2 inches, for wall-hung vanities. Follow yours.

Set the Top

One-Piece Tops

Install the faucet and the drain assembly on the top before you set it. It is much easier on a bench than lying under a cabinet.

  1. Dry-fit the top. It should sit flat on the cabinet with an even overhang and touch the wall.
  2. Scribe a gap at the wall if needed, or plan to close a small gap with the backsplash and sealant.
  3. Apply sealant in dabs or a bead along the top edges of the cabinet, using silicone or the adhesive the top maker calls for.
  4. Set the top straight down, centered, and press it into the sealant.
  5. Check level across the sink rim. Water should drain into the bowl, not pool at the front.

Stone and Vessel Tops

  • Stone tops are cut by a fabricator from the vanity and sink, and they need the same level, solid cabinet as a kitchen top.
  • Vessel sinks sit on top of the counter. They need the faucet height and drain type the sink maker calls for, and a vessel without an overflow needs a drain made for that.

Backsplash

  1. Dry-fit the backsplash on the top against the wall.
  2. Run a bead of silicone or the maker's adhesive on its bottom edge and back.
  3. Press it into place and tape it to the wall while it cures, if needed.
  4. Seal the joint between the backsplash and the top, and between the top and any side wall, with silicone or a kitchen and bath sealant. Tool the bead.

Connect and Test

The faucet, drain and trap connect as on any sink: supply lines hand tight plus a small turn, a trap arm that slopes down toward the wall, and no flexible corrugated trap parts. If the drain stub is too high or too low for a proper trap, or the trap arm would run uphill, stop and call the plumber.

  1. Open the stops slowly.
  2. Run hot and cold for a minute.
  3. Fill the sink, then pull the stopper to send a full bowl of water through the trap.
  4. Wipe every joint dry, then hold a dry paper towel under each one. Any damp spot is a leak.
  5. Check again after an hour, and again before you leave.

Common Mistakes

Mistake What it costs
Ordering a wider vanity without measuring the toilet Fails the 15-inch clearance, and the vanity goes back
Holes cut from the wrong edge A cabinet back with extra holes, or a new cabinet
Forcing the cabinet over the stubs A cracked fitting or a leak inside the wall
Wood shims under the cabinet Rot after the first leak
Faucet installed after the top is set An hour on your back in a cabinet
Grout or no sealant at the backsplash Water behind the top and swollen particleboard
Wall-hung vanity on anchors A vanity that pulls off the wall

Check Your Understanding

1. The toilet's centerline is 36 inches from the side wall. What is the widest vanity that fits against that wall?

21 inches, which leaves the 15 inches the code calls for. Standard sizes near that are 18 and 21 inches, so check what is available.

2. You remove an old vanity and find soft, stained subfloor under it. What do you do?

Stop and report it. Find and fix the leak, and repair the floor before the new cabinet goes in.

3. The new vanity's cabinet back is solid. The drain stub is 13 inches from the cabinet's left edge and 18 inches up. What do you cut?

A hole about 2 inches across for a 1-1/2-inch drain, centered 13 inches from the left edge and 18 inches above the bottom of the back, or a larger opening that clears the drain and both supplies.

4. A homeowner asks you to hang a floating vanity on the drywall with heavy-duty anchors. What do you tell them?

No. A wall-hung vanity needs solid blocking or the maker's bracket fastened into studs. The wall has to be opened to add blocking if none is there.

Key Takeaways

  • Shut off and test the stops, and check for hidden water damage when the old vanity comes out.
  • Keep 15 inches from the toilet's center to the vanity and 21 inches clear in front, or what your adopted code requires.
  • Measure the stubs from the same edges you mark on the cabinet, and test-fit before fastening.
  • Level with composite shims and fasten through the back rail into studs.
  • Seal the top and backsplash with silicone, and leak-test every joint more than once.