Most windows sold today replace old ones in existing homes and apartments. The new window has to fit an opening that may be out of square, sealed with old paint, rotted at the sill or full of lead dust. Measuring wrong means a window that does not fit and cannot be returned, since most replacement windows are made to order. And in older buildings, rules about lead paint and escape openings apply before the old window comes out.

This guide focuses on insert windows, also called pocket windows, which fit inside the existing frame. It also covers when to choose a full-frame replacement instead. The window maker's measuring guide and installation instructions control, and they differ from brand to brand.

What You Will Be Able to Do

  • Decide between an insert and a full-frame replacement.
  • Know the lead, asbestos, egress and safety glass rules that apply to replacement work.
  • Measure an existing frame and order the right size.
  • Remove old sashes and prepare the frame without damaging the exterior stops.
  • Set, shim, fasten and seal an insert window, and test it.

Insert or Full Frame?

Choose When
Insert The old frame is square enough, sound and dry. The exterior trim and siding stay. Fast, with less mess and less disturbance
Full frame The frame or sill is rotted, the opening leaks, or you want the full glass area back. The old frame, trim and some siding come out

An insert sits inside the old frame, so the glass area gets a little smaller on every side. It relies on the old frame's flashing and weather barrier, so it is the wrong choice where the old opening already leaks into the wall.

A full-frame replacement is installed like a new-construction window in an existing wall. The new flashing has to tie into the existing weather barrier in shingle order, which usually means removing some siding around the opening.

Rules to Check Before You Start

Lead Paint

In a home or child-occupied facility built before 1978, window replacement is always covered by EPA's Renovation, Repair, and Painting Rule (40 CFR 745), no matter how small the job. The minor-repair exception does not apply to window replacement. That means:

  • The company must be an EPA-certified firm, with a certified renovator directing the work.
  • The owner and occupants get the EPA lead pamphlet before work starts.
  • Work areas are contained, banned methods are not used, and cleanup is verified.

If you are not working under a certified renovator, stop before you pry the first stop. Some states run their own programs with stricter rules.

Asbestos in Old Putty and Caulk

Old window glazing putty and caulk can contain asbestos. EPA and state agencies list them among materials that may. On older windows, ask whether the materials have been tested before you cut or scrape a lot of putty or caulk, and follow your employer's plan.

Escape Openings

Bedroom windows are often a room's required emergency escape opening. Under the International Residential Code, a replacement window is exempt from the escape opening's minimum size and maximum sill height if both of these are true:

  1. It is the maker's largest standard size that fits the existing frame or rough opening, and it is the same operating style as the old one or a style that opens at least as much.
  2. It is not part of a change of occupancy, such as turning a garage into a bedroom.

Switching a casement to a double-hung of the same frame size can cut the opening a lot. Check the new window's net clear opening against the old one. Some states and cities do not adopt this exception, so check locally.

Safety Glass

The safety glazing rules still apply to the new window. A replacement window beside a tub, next to a door, near stairs, or large and low near a walkway may need tempered or laminated glass even if the old one had plain glass. Order it with the window.

Measuring for an Insert

Measure the opening inside the old frame, where the new window will sit.

  1. Width. Measure between the side jambs at the top, the middle and the bottom. Measure from jamb surface to jamb surface, not to the stops or the parting beads. Use the smallest.
  2. Height. Measure from the head jamb to the sill at the left, the center and the right. On a sloped sill, measure to the point the maker's guide shows. Use the smallest.
  3. Square. Measure both diagonals of the opening. A big difference means the frame is out of square and the insert must be small enough to square up inside it.
  4. Depth. Measure the depth available between the interior stop and the exterior stop, the strips that hold the sash in. The insert's frame must fit in that depth.
  5. Apply the maker's deduction. Most makers have you subtract a set amount from the smallest measurement, so there is room to shim. Use the number in their guide.

Worked Example: Order Size

You measure an old double-hung frame.

  • Widths: 34-1/4, 34-1/8 and 34-3/16 inches. Smallest: 34-1/8.
  • Heights: 54-1/2, 54-3/8 and 54-1/2 inches. Smallest: 54-3/8.
  • Diagonals: 64-3/8 and 64-5/8 inches, so the frame is out of square by 1/4 inch.

If this maker's guide says to deduct 1/4 inch from each smallest measurement, the order size is 33-7/8 by 54-1/8 inches. Write the numbers down in width by height order, and have a second person check them. A window ordered 1/2 inch too big will not go in, and one too small leaves gaps to fill.

Removing the Old Sashes

The steps below are for a common wood double-hung window. Work wet and keep dust down on older painted parts, following the lead-safe plan.

  1. Score the paint where the interior stops meet the frame, with a utility knife, so paint does not tear off the frame.
  2. Pry off the interior stops gently with a stiff putty knife and a flat bar. Save them if they will be reused.
  3. Remove the lower sash. Cut or unhook the sash cords and let the weights drop into their pockets.
  4. Remove the parting beads, the thin strips between the two sashes.
  5. Remove the upper sash the same way.
  6. Leave the exterior stops, also called blind stops, in place. The new insert seals against them.
  7. Deal with the weight pockets. Pull the weights out through the access panels if there are any, and fill the pockets with insulation. Open pockets are a major air leak.
  8. Clean and inspect the frame. Scrape loose paint and old sealant. Probe the sill and the bottom of the jambs with an awl. Wood that is soft for more than a short depth needs repair or a full-frame replacement.

Setting the Insert

  1. Dry-fit it. Set the window in the opening from inside to check fit before any sealant goes on. Remove it.
  2. Apply sealant where the maker shows, usually a continuous bead on the inside face of the exterior stops at the head and sides, and on the sill. Use a sealant compatible with the window frame.
  3. Set the window into the opening from inside, pressing it against the sealant at the exterior stops. Many sill angles or sill adapters fill the slope of an old sill. Install them as the maker shows.
  4. Shim the sides at the fastener holes in the side jambs, and under the sill at the corners if the maker allows. Shims keep the frame straight where the screws go.
  5. Check square and level. Measure the new window's diagonals, check the sill with a level, and check that the sash closes evenly against the frame.
  6. Fasten through the predrilled holes in the side jambs, through the shims, into the old frame. Drive the screws snug, not tight. A screw pulled tight bows the jamb in.
  7. Test the sash. Open, close and lock every sash. If a sash binds, back out the screws on that side, adjust the shims, and drive them again.

Sealing Inside and Out

  • Inside: fill the gap between the insert and the old frame with low-expansion foam made for windows, or backer rod and sealant. Reinstall the interior stops or new trim.
  • Outside: seal the joint between the new frame and the exterior stops or trim with an exterior sealant the window maker approves.
  • Never seal over weep holes in the bottom of the new frame. They let water that gets into the frame drain out.
  • Exterior trim is often covered with formed aluminum or new trim at the same time. That is trim and siding work, and it must not block drainage.

Warning: When you work on an upper floor, an open window opening can be a fall hazard. Insert windows usually go in from inside. Keep the old sash, the new window and your body inside the room, and never lean out to reach. A window that slips can fall on people below, so keep the area under the window clear.

Handling the Old and New Windows

  • Old sashes are heavy, and old glass breaks easily. Wear cut-resistant gloves and eye protection.
  • Carry glass on edge.
  • Bag or wrap old sashes and debris from a pre-1978 job as the lead-safe plan requires.

Common Mistakes

Mistake What it costs
Replacing pre-1978 windows without a certified renovator Lead dust in the home and fines for the firm
Measuring to the parting beads or stops A window that is too small
Using the largest measurement A window that will not fit
Insert into a rotted frame Leaks and rot behind a new window
Smaller-opening style in a bedroom A window that no longer meets escape rules
Screws driven tight Bowed jambs and binding sash
Sealant over weep holes Water trapped in the frame

Check Your Understanding

1. A landlord wants one cracked window in a 1962 apartment replaced quickly and asks if it is under the small-job limit. What do you say?

No. Window replacement in pre-1978 housing is always covered by the RRP rule, whatever its size. It needs a certified firm and renovator and lead-safe work practices.

2. Your width measurements are 30-1/2, 30-3/8 and 30-5/8 inches. Which do you use?

30-3/8 inches, the smallest, and then the maker's deduction.

3. The sill is soft to an awl at both corners. Do you install an insert?

No. An insert needs a sound frame. Repair the frame, or switch to a full-frame replacement so the rot can be removed and the opening flashed properly.

4. An owner wants to replace a bedroom casement with a double-hung of the same frame size. What do you check?

The new window's net clear opening. A double-hung opens only about half its height, so it may not meet the escape rules, and the replacement exception needs the same style or one that opens as much.

5. After you fasten the insert, the lower sash sticks halfway up. What do you do?

Back out the side screws, check for a bowed jamb, adjust the shims so the jamb is straight, and refasten snug, not tight.

Key Takeaways

  • Inserts need a square, sound, dry frame. Otherwise, go full frame.
  • Pre-1978 window replacement is always RRP work, and old putty and caulk may contain asbestos.
  • A replacement window keeps escape and safety glass rules in mind, including the same-style condition.
  • Measure in three places each way, use the smallest, and apply the maker's deduction.
  • Shim at the fasteners, drive screws snug, seal inside and out, and keep weep holes open.