Set terminal and line posts, assemble the top rail and fittings, stretch chain-link fabric to the right tension, tie it off, and hang gates that cannot be lifted off.

Table of contents

Chain-link fence is a steel frame with woven wire fabric stretched across it. Its strength comes from tension. The heavy posts at the ends, corners and gates, called terminal posts, hold the fabric taut, and the lighter line posts in between only keep it in line. If the terminal posts lean, or the fabric is loose, the whole fence sags. If the fabric is pulled too tight, it bends the posts and rail.

The steps below follow common manufacturer practice. Post sizes, hole depths and fitting counts depend on fence height, wind, soil and frost, and the job specification, the kit's instructions and your local rules win. Commercial work often follows ASTM F567, the standard practice for installing chain-link fence.

What You Will Be Able to Do

  • Name the parts of a chain-link fence and what each one does.
  • Lay out and set terminal and line posts to the right heights.
  • Assemble fittings and top rail on the posts.
  • Stretch fabric to the right tension and tie it off.
  • Hang a gate so its hinges cannot be lifted off.

Parts

Part What it does
Terminal post Larger post at each end, corner and gate. Takes the fabric's pull
Line post Smaller post between terminals. Holds the line and the top rail
Top rail Pipe along the top that keeps the posts in line
Loop cap Cap on a line post with a hole the top rail slides through
Tension band Flat clamp on a terminal post that holds the tension bar
Brace band Clamp that holds a rail end cup to a terminal post
Tension bar Flat bar woven through the end of the fabric
Tie wire Wire clip that fastens fabric to line posts and top rail
Tension wire Wire along the bottom that keeps the fabric from pushing out

Choosing Fabric

  • Height is the fabric's height, such as 4 or 6 feet.
  • Mesh is the size of the diamond. Two inches is common for yards.
  • Gauge is the wire thickness. A lower number means thicker wire.
  • Coating is galvanized, aluminized or vinyl. Vinyl-coated fabric uses matching coated posts and fittings.
  • Selvage is the finish at the top and bottom edges. A knuckled edge is bent back and smooth. A twisted edge leaves sharp points. Put knuckled edges where people touch the fence.

Residential kits pair larger terminal posts with smaller line posts and a lighter top rail. Use the sizes the job calls for. Do not swap line posts in as terminals to save money.

Layout

  1. Confirm the property line, the permit and any pool barrier rules, and get utilities marked through 811 before you dig.
  2. Stake every terminal post first: ends, corners and both sides of each gate. Many installers set them about 4 inches inside the property line so the concrete stays on the owner's land.
  3. Gate openings. Many makers sell gates by the clear opening between posts, so a gate for a 36-inch opening needs exactly 36 inches between the inside faces of the posts, with the hinge and latch clearance built into the gate. Check the gate's label before you set those posts.
  4. Line posts. Space them evenly between terminals, typically no more than 10 feet on center. Divide each run into equal spaces.

Setting Posts

Holes

Terminal posts take far more load than line posts, so their holes are wider and deeper. One manufacturer's guide suggests terminal holes about 8 inches wide and 18 to 30 inches deep, and line post holes about 6 inches wide and 18 to 24 inches deep. Taller fences, high wind and frost all push those numbers up. Some specifications add depth for each foot of fence height. Where the ground freezes, go below the frost line. Keep the sides straight.

Terminal Posts

  1. Mark the ground line on each post with chalk or crayon. A common kit setup has terminal posts standing about 2 inches taller than the fabric.
  2. Set the post in the center of the hole, in concrete.
  3. Plumb it on two sides with a level, and keep the ground-line mark at grade.
  4. Crown the concrete so it slopes away from the post and sheds water.
  5. Let the concrete harden before you pull against these posts. One maker suggests about 24 hours before you string line posts from them. Wait longer, as the concrete maker says, before you stretch fabric.

Line Posts

  1. Stretch a string tight between terminal posts on the outside face, about 4 inches below the terminal tops.
  2. Set each line post so its center lines up with the terminal post centers. Because line posts are smaller, their outside faces sit just inside the string.
  3. Set the line post tops even with the string. With the loop caps on, the top rail will then run level with the top of the fabric. Use the height chart for your kit.
  4. Set them in concrete, plumb, and crown the tops.

Fittings and Top Rail

  1. Tension bands. Slide them onto each terminal post, spaced evenly up the post, often about 12 inches apart. Follow your kit's count. A corner post gets a set for each direction. The long flat side faces the outside of the fence, where the fabric goes.
  2. Brace bands and rail ends. Add a brace band and a rail end cup on each terminal post where the top rail will land.
  3. Post caps go on the terminal posts. Loop caps go on the line posts, with the flat side facing out.
  4. Bolt direction. Put carriage bolt heads on the outside of the fence and the nuts on the inside, so nobody can loosen them from outside.
  5. Top rail. Slide rail through the loop caps from one terminal post to the next. Join lengths with the swaged end of one pipe pushed into the next, or with sleeves. At the far terminal, measure, cut the rail to fit snugly into the rail end cup, and bolt it.
  6. Bracing. Taller fences and long runs often get a brace rail from each terminal post to the first line post, with a truss rod. Follow the specification.

Cut pipe with a pipe cutter or a saw with a metal-cutting blade. Wear eye protection, and a face shield with an abrasive blade, which throws sparks and hot fragments.

Hanging and Stretching Fabric

Hanging

  1. Unroll the fabric along the outside of the fence line, from one terminal post toward the next.
  2. Slide a tension bar through the end row of diamonds.
  3. Bolt the tension bar to the tension bands on the first terminal post, with bolt heads outside.
  4. Stand the fabric up against the frame, walking it along and taking out slack.
  5. Hook it loosely to the top rail with a few tie wires to hold it while you stretch.

Stretching

Warning: Stretched fabric stores a lot of energy. A slipping pull bar or a failed stretcher can snap the fabric back. Stand to the side of the pulling line, wear cut-resistant gloves and safety glasses, and keep others clear.

  1. Weave a second tension bar, the pull bar, through the fabric about 3 feet in from the loose end.
  2. Hook a fence stretcher or come-along from the pull bar to the far terminal post, below the top rail.
  3. Pull slowly, a few clicks at a time, and walk the line to see that the fabric rises evenly.
  4. Stop when the fabric gives only slightly when you squeeze it by hand. Over-stretching bends the terminal posts and bows the top rail.
  5. Remove extra fabric by taking out one strand of wire. Open the bent knuckles at the top and bottom of a single strand with pliers, then spin that strand up and out of the links until the fabric comes apart. You do not cut the fabric.
  6. Weave the final tension bar through the end of the fabric and bolt it to the tension bands. Then release the stretcher.

To join two rolls, take a single strand from the end of one roll and wind it down through the end links of both, like a corkscrew. Then bend and tighten its knuckles at the top and bottom.

Tying Off

  1. Fasten the fabric to the top rail with a tie about every 24 inches.
  2. Fasten it to each line post with a tie about every 12 inches.
  3. Twist tie ends tight and bend them in, so no sharp ends stick out where people walk.
  4. Tighten the nuts on all tension and brace bands.
  5. Bottom. Run a bottom tension wire, pulled taut and hog-ringed to the fabric, or a bottom rail if the job calls for one. This keeps the bottom from pushing out where dogs or children lean on it.

On rolling ground, chain-link follows gentle slopes. Fill dips under the fabric with soil so the bottom stays close to grade. At a sharp change in grade, set a terminal post there and treat each side as its own run.

Gates

  1. Mount the post hinges on the gate post. Set the top hinge with its pin pointing down and the bottom hinge with its pin pointing up. With the pins opposed, nobody can lift the gate off its hinges.
  2. Set the gate in place with its top level with the top of the fence.
  3. Adjust the hinges so the gate swings fully without dragging.
  4. Mount the latch at a height that is easy to use, or where the pool barrier code requires it, and tighten every bolt.
  5. On a double drive gate, add a drop rod on the inactive leaf and a keeper in the ground or pavement.

Common Mistakes

Mistake What it costs
Line posts used as terminal posts Posts bend under fabric tension
Stretching before the concrete has cured Terminal posts pull out of plumb
Over-stretching the fabric Bent posts and a bowed top rail
Too few ties on line posts Fabric that pulls away and sags
Both gate hinge pins pointing up A gate that can be lifted off
Sharp tie ends and twisted selvage at hand height Cuts to people and pets

Check Your Understanding

1. A run between terminal posts is 53 feet. How do you space line posts at no more than 10 feet?

53 / 10 = 5.3, so use 6 equal spaces of 53 / 6 = 8 feet 10 inches, with 5 line posts.

2. You finished stretching and the fabric does not move at all when you squeeze it, and the far end post now leans in. What happened?

The fabric was over-stretched. Release some tension, replumb the terminal post if its concrete will let you, and stretch until it gives slightly.

3. You have 2 feet of extra fabric at the end of a run. How do you remove it?

Open the top and bottom knuckles of one strand with pliers and spin that strand out. The fabric separates without cutting.

4. How do you set the hinges so the gate cannot be lifted off?

Top hinge pin pointing down and bottom hinge pin pointing up.

Key Takeaways

  • Terminal posts take the fabric's pull, so give them the bigger posts and the deeper holes.
  • Let terminal concrete cure before you pull against it.
  • Space line posts evenly, typically no more than 10 feet apart.
  • Stretch until the fabric gives slightly by hand, then tie about every 24 inches on the rail and 12 inches on posts.
  • Bolt heads go outside, and gate hinge pins oppose each other.