Exterior trim frames the house: corner boards, window and door casings, frieze boards under the eaves and bands between floors. It hides the cut ends of the siding and gives the walls clean lines. It also creates a ledge on top of every piece, and every ledge catches water. Trim that is not flashed on top sends that water straight behind the siding, where it rots the sheathing around windows and doors first.

This guide covers the three common trim materials and the flashing that goes with them. Follow the trim maker's instructions and the siding maker's details, because the siding system often decides how trim goes on.

What You Will Be Able to Do

  • Choose a trim material and match fasteners and finish to it.
  • Build outside and inside corner boards with even faces.
  • Flash the top of window and door casings and horizontal trim so water drains out.
  • Fasten and join PVC trim so it can move without opening up.
  • Seal the right joints and leave the drainage gaps open.

Trim Materials

Material Strengths Needs
Wood, primed pine or cedar Easy to cut and shape Prime all sides and ends, paint, keep off wet surfaces
Engineered wood Long, straight, primed Seal every cut, follow the maker's gaps
Fiber cement Does not rot or burn easily Silica dust control when cutting, heavy, brittle
Cellular PVC Will not rot, needs no paint Moves with heat, needs glued joints and the right fasteners

Order of Work

  1. Water-resistive barrier (WRB) on the walls, and window and door flashing in place.
  2. Corner flashing behind each outside and inside corner.
  3. Corner boards.
  4. Window and door casing, with head flashing above.
  5. Frieze boards and trim bands, with Z-flashing above where needed.
  6. Siding, which butts into the trim.
  7. Sealant at the trim-to-siding joints the maker calls for.

Most wood, engineered wood and fiber cement siding systems put trim on first and butt the siding into it. Some allow trim to go on over the siding. Vinyl usually uses its own corner posts and J-channel, though wood or PVC trim can be added with the right receiver. Check the siding system's details before you start.

Before You Start

  • Prime wood trim on all six sides, including the back and both ends, before it goes up.
  • Store trim flat and dry. A twisted board stays twisted on the wall.
  • Match fasteners to the material. Use hot-dipped galvanized or stainless nails on wood, and the fasteners the maker lists for engineered wood, fiber cement and PVC. Plain steel rusts and stains.
  • Cut fiber cement trim outdoors with a saw that has working dust collection, or with shears, the same as fiber cement siding.
  • Plan access. Corner boards and frieze boards run up to the eaves. Use scaffolding or a lift above the first floor, and follow your fall protection plan.

Corner Boards

Outside Corners

An outside corner board is two boards meeting at the corner. One board overlaps the edge of the other. If both boards are the same width, the overlapping side looks wider by the thickness of the board. To make both faces look the same, make the overlapping board wider by one board thickness.

Worked Example: Even Corner Faces

You are using 5/4 PVC trim, which is 1 inch thick.

  • Board A is a 5/4 x 4, which is 3-1/2 inches wide.
  • Board B overlaps the edge of board A. Make it 3-1/2 + 1 = 4-1/2 inches wide, which is a 5/4 x 5.
  • From board A's wall you see A's 3-1/2-inch face plus B's 1-inch edge, or 4-1/2 inches. From board B's wall you see B's 4-1/2-inch face. Both sides read 4-1/2 inches.

Building and Hanging

  1. Flash the corner first. Lap a strip of flashing or WRB around the corner, in shingle order with the wall WRB.
  2. Build the corner on the ground. Join the two boards along their edge with fasteners and, for PVC, PVC cement. A pre-built corner goes up straight and stays tight.
  3. Set the bottom. The bottom of the corner board follows the same clearance to grade, roofs and decks as the siding. Seal or prime the bottom end.
  4. Set the top. Run it up to the soffit or frieze board.
  5. Plumb it and fasten it into the framing on both walls, at the spacing the maker lists.

Inside Corners

Inside corners are often a single square strip or one flat board, with the siding on both walls butting into it. Flash behind the corner first, just like an outside corner.

Window and Door Casing

Exterior casing frames the opening. On a typical job it goes on after the window is installed and flashed, and before the siding.

  1. Check the window flashing. The sill pan, jamb and head flashing must already be done in the right order, with the WRB lapped over the head flashing.
  2. Set the sill or bottom piece if the design has one. Slope its top surface away from the window so it sheds water.
  3. Set the side casings, plumb and tight to the window frame, leaving any gap the window maker calls for.
  4. Set the head casing across the top, level.
  5. Flash the head casing. See the next section.

Joints

  • Butt joints at corners are the most common exterior detail. A miter looks good on day one, but outdoors it opens as the wood moves, and the open joint catches water.
  • Scarf joints for long runs. Where two pieces must join end to end, cut both ends at a matching 45-degree angle so they overlap. Glue PVC scarfs, and seal wood scarfs, with the upper piece lapping over the lower one so water flows over it.

Head Flashing and Drip Cap

The IRC calls for flashing at the heads of windows and doors and continuously above all projecting wood trim. That means a metal or plastic drip cap on top of every head casing and every horizontal band.

  1. Cut the drip cap a little longer than the casing, so it runs past each end of the casing.
  2. Set it on top of the casing, with its front lip over the face of the casing and its vertical leg flat against the wall.
  3. Lap the WRB over the vertical leg. Slit the WRB above the casing if needed, slide the leg up behind it, and tape the slit in shingle order. Water running down the WRB must land on the front of the drip cap, never behind it.
  4. Shape the ends so water drips off past the casing, not down the end grain or behind the side casings.
  5. Leave a gap above it. Siding above a drip cap stops short of the flashing. One major engineered wood maker calls for 3/8 inch, and one major fiber cement maker calls for 1/4 inch above horizontal flashing. Do not caulk that gap.

Warning: Do not caulk the bottom edge of a drip cap or the gap between the drip cap and the siding above. Those gaps are the way out for water that gets behind the siding.

Frieze Boards and Trim Bands

A horizontal band between floors is a long ledge. Flash it with a Z-flashing, lapping its upper leg behind the WRB. One major engineered wood maker calls for an upper leg at least 4 inches tall, and adhesive flashing to extend it if the leg is shorter. A frieze board tight under the soffit is protected from above and usually does not need the same flashing, but follow the plans.

PVC Trim

Cellular PVC trim cuts and machines like wood and never rots, but it grows and shrinks with temperature far more than wood. Makers publish their own movement figures and fastening rules, so read them for the product on the job.

  • Fasten it well. Makers commonly call for fasteners every 12 to 16 inches along the board and close to each end, roughly within 2 inches. Use the stainless or coated trim screws or nails they list, and two fasteners across wide boards.
  • Glue the joints. Glue scarf joints and corners with PVC cement so movement does not open them.
  • Leave room where it meets the house. Follow the maker's gap rules where PVC meets other materials.
  • Fill fastener holes with the maker's filler, or use plugs.
  • Paint is optional. If the owner wants paint, check the maker's paint rules first, since some colors make PVC run hot and move more.
  • Cut with a carbide blade and wear eye protection. PVC chips are sharp and fly far.

Wood and Engineered Wood Trim

  • Prime every surface of solid wood trim before installation, and prime every cut end on the job.
  • Keep it off horizontal surfaces. End grain sitting on a deck, roof or concrete drinks water and rots. Hold the bottom up by the same clearance as the siding.
  • Seal cuts on engineered wood trim with paint or sealant, as the maker requires.
  • Nail into framing, and set and fill the nails if the trim will be painted.

Sealing

Seal the vertical joints where siding meets corner boards and casings, using the sealant the siding maker lists, often one meeting ASTM C920. Leave the drainage gaps open: the bottom edges of siding, the gap above drip caps and Z-flashing, and any weep holes.

Common Mistakes

Mistake What happens
No drip cap above a head casing Water runs behind the siding and rots the wall under the window
WRB tucked under the drip cap's leg Water from above goes behind the flashing
Caulking the gap above a drip cap Trapped water rots the sheathing
Mitered outside corners on wood Joints open, and end grain soaks up water
Same-width boards at a corner One side looks fatter than the other
PVC trim with too few fasteners Boards bow and joints open in the sun
Unprimed wood trim ends Rot starts at the cut
Trim sitting on a roof or deck The bottom end rots

When to Stop

  • Rotted sheathing or framing around a window or door. Soft sheathing gets replaced, and damaged framing, headers or sills go to the supervisor or a qualified carpenter.
  • A window or door that leaks after trim is removed. Find the leak before new trim covers it.

Check Your Understanding

1. You are building an outside corner from 1x trim that is 3/4 inch thick. One board is 3-1/2 inches wide. How wide should the overlapping board be?

3-1/2 + 3/4 = 4-1/4 inches. Then both sides of the corner show the same 4-1/4-inch face.

2. A coworker set a drip cap on a head casing and stuck the WRB to the front of it with tape, so the drip cap's leg sits on top of the WRB. Is that right?

No. The WRB must lap over the drip cap's vertical leg, so water running down the WRB lands on the outside of the flashing. Slit the WRB, tuck the leg behind it, and tape the slit in shingle order.

3. A homeowner points to the small gap between the siding and the drip cap over a window and asks you to caulk it. What do you say?

That gap lets water that gets behind the siding drain out. Sealing it would trap water against the wall, so it stays open.

4. Why do exterior corners on painted wood trim usually use butt joints instead of miters?

Wood moves with moisture, so outdoor miters open up and expose end grain to water. A butt joint stays closed and sheds water better.

Key Takeaways

  • Every piece of trim with a top edge needs flashing above it, with the WRB lapped over the flashing.
  • Leave the gap above drip caps and Z-flashing open, and seal only the joints the maker names.
  • Make the overlapping corner board wider by one board thickness so both faces match.
  • Prime wood on all sides and seal every cut, and keep trim ends off roofs, decks and concrete.