Installing Housewrap and Weather Barriers
Lay out, lap, fasten and tape a housewrap or felt weather barrier so every layer sheds water, then seal penetrations and repair tears before the siding covers it.
Table of contents
Siding is not waterproof. Rain blows through laps, joints and gaps around trim, and some of it always reaches the wall behind. The layer that stops that water is the water-resistive barrier (WRB), a sheet or coating over the sheathing that sheds water down and out. A WRB with one backward lap or an untaped tear can let water soak the sheathing for years before anyone sees a stain inside.
This guide covers the field of the wall: rolls, laps, fasteners, seams, penetrations and repairs. Windows and doors get their own flashing sequence, and the WRB ties into it.
What You Will Be Able to Do
- Explain why every WRB lap must shed water and spot a reverse lap.
- Plan roll courses for a wall and work out how much wrap to order.
- Start, lap, fasten and tape housewrap the way the code and the maker require.
- Seal pipes, vents, boxes and other penetrations in shingle order.
- Patch tears and holes so the barrier works again.
Terms
- Drainage plane: the surface water runs down once it gets past the siding. The WRB is the drainage plane.
- Housewrap: a synthetic sheet sold in rolls, such as spun or woven plastic. Some are textured or creased to drain faster.
- Felt or building paper: asphalt-saturated felt or kraft paper, the older WRB types. They go on the same way, in shingle order.
- Cap fastener: a nail, staple or screw with a wide plastic cap that holds wrap without tearing it.
- Shingle lap: upper layers lap over lower layers, like roof shingles.
- Reverse lap: any spot where a lower layer sits on top of an upper one, so water runs behind it.
- Rainscreen: a small air gap between the WRB and the siding, made with furring strips or a spacer mat, so water drains and the wall dries.
Which Barrier
| Type | Where it fits | Watch for |
|---|---|---|
| Standard housewrap | Most vinyl, wood and fiber cement walls | Sun exposure limit, tape compatibility |
| Drainable housewrap | Wet climates, fiber cement, wood | Install with grooves running up and down |
| Felt or building paper | Older homes, some stucco systems | Tears easily, needs careful laps |
| Fluid-applied membrane | Commercial walls, complex shapes | Thickness and cure time per maker |
| Coated sheathing panels | New framing with taped panel seams | Every seam taped, a missed seam is a leak |
Stucco, adhered stone and brick have extra rules, such as two layers or an air space. Follow the plans and the cladding maker for those walls.
The Rules That Apply
The International Residential Code (IRC) requires at least one layer of WRB over the studs or sheathing of every exterior wall. For No. 15 felt and housewraps meeting ASTM E2556, the code calls for horizontal courses with the upper layer lapped over the lower one by at least 2 inches, and joints lapped at least 6 inches. The barrier runs continuously to the top of the wall.
The maker's instructions usually ask for more than the code. One major housewrap maker, for example, calls for 6 inches of overlap on horizontal laps, 6 to 12 inches on vertical seams, and tape on every vertical seam. The warranty depends on following them, and the adopted code and local amendments can add rules. When the two differ, follow the stricter one.
Before You Start
- Know the order of work. The best time to wrap a wall is after the roof sheathing and the roof-to-wall step and kickout flashing are in, and before windows go in. If windows are already installed, the WRB still has to end up in shingle order around them.
- Check the sheathing. Replace soft, delaminated or rain-soaked panels. Wrap does not fix a bad substrate.
- Check compatibility. Use the tape and flashing the wrap maker lists. Some tapes do not stick to some wraps, and some sealants attack them.
- Check the weather. Tape needs a clean, dry, frost-free surface and a temperature in its listed range.
- Plan to cover it. Housewrap breaks down in sunlight. One major maker requires its standard wraps to be covered within 120 days. Check the limit for your product, and do not wrap a house weeks before the siding crew arrives.
- Plan safe access. Wrap and flashing release paper are slippery. Never walk on them. Above the first floor, use scaffolding or a lift instead of leaning a ladder against loose wrap, and follow your fall protection plan.
Installing Housewrap
- Start low. Begin at a bottom corner of the lowest wall so every later course laps over the one below it.
- Set the bottom edge. Hold the roll plumb at the corner. Let the bottom edge hang past the joint between the sill plate and the foundation. One maker requires at least 1 inch and recommends 2 inches or more. On a slab, run it to the bottom of the sill plate. Where there is a base flashing or weep screed, lap the wrap over it.
- Wrap the corner. Unroll past the corner and onto the next wall. A corner is a weak spot, so never end a sheet right on it.
- Fasten as you go. Drive cap fasteners into the studs or wood sheathing along stud lines. One maker spaces them no closer than 6 inches and no farther than 18 inches apart. Plain staples without caps tear out in wind and are allowed only as a temporary hold where the maker permits it.
- Unroll right over openings. Do not cut around a window or door opening yet. The flashing method decides how the wrap is cut there. Keep fasteners back from the edges of the opening, where flashing will go.
- Make vertical seams. Where one roll ends and the next starts, overlap the seam by the amount the maker requires and tape it.
- Lap the next course over. Start the second course so it laps over the top of the first by at least 6 inches, or more if the maker says so. Keep working up the wall until the barrier reaches the top plate or the roof sheathing.
- Tape horizontal seams if required. Many makers make horizontal seam tape optional for a water barrier but required when the wrap is also the air barrier. Follow the plans.
- Cover every wall. Wrap gable ends, the walls behind porches, and garage and other unheated walls too. Water does not care whether a room is heated.
- Lap over roof flashing. Where a wall meets a roof, the wrap laps over the step flashing and kickout flashing. If the wrap is tucked behind them, water running down the wall goes behind the flashing.
- Walk every lap. Before siding starts, look at each seam from bottom to top and fix reverse laps, loose flaps and tears.
Warning: Do not climb or step on wrap that is lying on a roof or deck. It is as slick as ice, wet or dry.
Worked Example: Planning Courses
A one-story house has 136 feet of wall around it. The wall is 9 feet 6 inches tall from the bottom of the sill plate to the top plate, and you have 9-foot rolls that are 150 feet long. You want 2 inches over the foundation joint and a 6-inch horizontal lap.
- Course 1 starts 2 inches below the sill plate joint, so it covers the wall up to 8 feet 10 inches.
- Course 2 must lap 6 inches over course 1, so its bottom edge sits at 8 feet 4 inches. That leaves only 1 foot 2 inches to the top plate. A full 9-foot roll would waste most of its width, so a narrow roll of 3 feet works better there.
- Length per course: 136 feet plus about 1 foot of vertical lap at each roll seam. At 150 feet per roll, each course takes one full roll with a seam or two.
- Order: one 9-foot roll and one 3-foot roll, plus gable pieces, tape and fasteners.
- Better option: a 10-foot roll hung 2 inches below the joint reaches 9 feet 10 inches, which covers the whole wall in one course with no horizontal seam at all. Fewer seams mean fewer places to leak.
Openings
Windows and doors are flashed by the window or door maker's method, in the order sill, jambs, head. The WRB above the opening must lap over the head flashing, never tuck behind it.
Penetrations
Pipes, dryer vents, hose bibs, light boxes and electrical meters all cut through the barrier. Each one must be sealed so water running down the wrap goes around it, not into it.
- Use a mounting block where you can. Many siding systems sell flashed blocks for lights, outlets, hose bibs and vents. A block with a flange gets flashed like a small window.
- Cut the wrap snug. Cut an X or a hole just large enough for the pipe or box. Do not leave a big opening.
- Flash in shingle order. Apply flexible flashing tape to the bottom first, then the sides, then the top, so each upper piece laps over the one below it.
- Round items need flexible flashing. Stretchable flashing wraps around a round pipe without wrinkles. Press every inch down.
- Slit and tuck for flanged items. Another method is to slit the wrap above the item and slide the top flange under the wrap, so the wrap laps over it.
- Roll the tape. Firm pressure with a hand roller makes the bond. A wrinkle is a channel that carries water behind the tape.
Horizontal Transitions
Where one cladding stops and another starts, such as siding over a stone base or at a horizontal trim band, a metal Z-flashing or L-flashing carries water out. The flashing laps over the material below. The WRB from above laps over the flashing's upper leg, or gets taped to it in shingle order.
Rainscreens
A rainscreen gap helps a wall dry, and some siding makers require one in wet climates or over foam sheathing. The gap comes from vertical furring strips, a plastic spacer mat, or a drainable wrap. The furring changes how far nails must reach, so follow the siding maker's fastening rules for a furred wall. Close the bottom and top of the gap with an insect screen so it stays open to air and water but not to bugs.
Repairing Tears and Holes
- Small tears: cover them with the wrap maker's tape, pressed down firmly.
- Holes over about 1 inch: cut a patch of wrap larger than the hole. Slit the wrap above the hole and tuck the top of the patch into the slit so it laps under the wrap above. Tape the bottom of the patch first, then the sides, then the top, so the tapes lap in shingle order.
- Big damage: replace the section and re-lap it into the courses around it.
Common Mistakes
| Mistake | What happens |
|---|---|
| Starting at the top of the wall | Every lap is backward and funnels water in |
| Wrap tucked behind step or kickout flashing | Roof runoff goes behind the barrier |
| Ending a sheet on a corner | Wind and water open the seam |
| Untaped vertical seams | Wind-driven rain gets behind the wrap |
| Plain staples left as the only fasteners | Wrap tears loose and flaps |
| Leaving wrap in the sun for months | It weakens, and the warranty is gone |
| Holes cut around pipes and left open | Water runs straight into the sheathing |
| Tape on dusty or wet wrap | Tape lets go in the first hot week |
Check Your Understanding
1. A new helper starts wrapping a wall by stapling the first roll along the top plate and working down. What is wrong, and what do you tell him?
Every course would lap under the one below it, so water runs behind each seam. Take it down and start at the bottom corner so each upper course laps over the lower one.
2. The siding crew will not arrive for five months. Should you wrap the house now?
No, not with a wrap that has a shorter exposure limit. Many standard wraps must be covered within about four months. Wrap closer to the siding date, or use a product rated for longer exposure.
3. You find the wrap tucked behind the step flashing where a wall meets a porch roof. What do you do?
Pull the wrap out and lap it over the step flashing and the kickout flashing. Tape it down if needed. Water running down the wall must stay on the outside of the flashing.
4. A dryer vent pipe pokes through the wall. In what order do the pieces of flashing tape go on?
Bottom first, then the sides, then the top. Each piece laps over the one below it, so water flows over the laps and not into them.
Key Takeaways
- The WRB, not the siding, keeps the wall dry, so every lap must shed water.
- Start at the bottom, lap upper courses over lower ones, and wrap past corners.
- The code sets the minimum laps, and the maker's instructions usually ask for more.
- Use cap fasteners, tape vertical seams, and keep the wrap out of the sun past its limit.
- Seal every penetration in shingle order and patch tears before the siding goes on.