Installing Roof Underlayment and Ice Barrier

15 min read Training Guide

Choose the right underlayment for the slope and climate, figure how far up the roof the ice barrier must reach, and lap and fasten each layer so it sheds water.

Table of contents

Shingles shed most of the water that hits a roof, but not all of it. Wind drives rain under the tabs, and ice dams push meltwater back up the slope. The layer under the shingles catches what gets through. It also keeps the deck dry between tear-off and shingling, and it is part of the tested fire rating for many shingles. A roof with good shingles over bad underlayment still leaks.

This guide covers underlayment and ice barrier under asphalt shingles on a wood deck. Rules here come from the 2021 International Residential Code (IRC), Section R905.1, and one major shingle maker's instructions. Your town may have adopted a different edition or local changes, and the shingle and underlayment makers' instructions apply on top of the code. Where two rules differ, follow the stricter one.

What You Will Be Able to Do

  • Pick an underlayment that the code and the shingle maker accept.
  • Apply one layer or two, depending on the slope.
  • Work out how far up the roof the ice barrier must reach.
  • Install self-adhering membrane in valleys and at walls without wrinkles or reverse laps.
  • Spot the mistakes that let water run under the layer meant to stop it.

Underlayment Types

Type Standard What to know
No. 15 asphalt felt ASTM D226 Type I Light, cheap, tears easily, wrinkles when wet
No. 30 asphalt felt ASTM D226 Type II Heavier, required in some high-wind areas
Felt for steep slopes ASTM D4869 Types I to IV by weight
Synthetic ASTM D8257 Light and strong, often slick, usually needs cap fasteners
Self-adhering membrane ASTM D1970 Sticks to the deck and seals around nails

The code requires listed underlayment to carry a label with its standard. Synthetic products are accepted through newer code editions or product evaluation reports, so confirm the product is approved where you work. Some shingle makers also require their own underlayment to keep the full warranty.

Self-adhering membrane (often called ice and water shield) seals around the nail shanks that go through it, so water backed up by an ice dam cannot follow the nails into the deck. That is why it goes at eaves, valleys and walls. When it covers a whole roof, it acts as a vapor retarder, so attic ventilation matters even more.

Layers by Slope

Slope is the rise in inches for each 12 inches of run, written 4:12 or 4/12. Asphalt shingles are allowed down to 2:12 (IRC R905.2.2), but low slopes need a double layer.

Slope Underlayment under the 2021 IRC
Below 2:12 Shingles not allowed. Use a low-slope system
2:12 up to 4:12 Two layers: a 19-inch starter strip at the eave, then 36-inch sheets each lapped 19 inches over the one below
4:12 and steeper One layer, shingle fashion, with 2-inch laps

At every slope, end laps are 4 inches and must be staggered at least 6 feet apart from course to course. The code also says any wrinkle or bump in the underlayment must not keep the shingles from sealing.

Worked Example: Double Coverage on a 3:12 Porch Roof

The porch roof is 12 feet from eave to wall, measured along the slope, or 144 inches.

  • The 19-inch starter strip covers the first 19 inches.
  • Each 36-inch sheet laps the one below by 19 inches, so each new sheet climbs 36 - 19 = 17 inches.
  • The first full sheet starts at the eave and reaches 36 inches. After that you need (144 - 36) / 17 = 6.4 more sheets, so plan on 7 more, or 8 full courses in all.
  • Every spot on the deck is now covered by at least two layers.

Fastening

Where the code does not require wind design, underlayment only needs enough fasteners to hold it in place until shingles cover it. The maker's instructions still control the fastener type and pattern, and many synthetics require plastic or metal cap nails, not staples. Follow the fastening marks printed on the sheet.

Where the code requires wind design (high-wind areas shown on the code's wind map), the rules tighten: ring-shank or deformed-shank nails with 1-inch caps, in a grid about 12 inches apart between laps and 6 inches apart along the laps. Your lead will know if your area is one of them.

Ice Barrier

Where It Is Required

Where the local building department has found a history of ice forming at the eaves and backing up water, the IRC requires an ice barrier (R905.1.2). It can be two layers of underlayment cemented together, but almost every crew uses self-adhering membrane. It must run:

  • From the lowest edge of every roof surface to a point at least 24 inches inside the exterior wall line of the building.
  • On roofs of 8:12 and steeper, the 2021 IRC also requires at least 36 inches measured along the slope from the eave edge. Code editions differ on this line, so check the edition your town uses.

Detached buildings with no heated space are exempt. Many crews put membrane at the eaves even where it is not required, because it is cheap insurance.

Worked Example: How Far Up the Roof?

The membrane is measured along the slope, but the 24-inch rule is measured level, from the outside face of the wall. Convert with the slope factor.

Slope Factor
4:12 1.054
6:12 1.118
8:12 1.202
10:12 1.302
12:12 1.414

Case 1. A 6:12 roof has a 16-inch overhang, measured level from the wall sheathing to the drip edge.

  • Level distance to cover = 16 + 24 = 40 inches.
  • Along the slope = 40 x 1.118 = 44.7 inches.
  • A 36-inch roll falls about 9 inches short. Run a second course above it, lapped as the maker says.

Case 2. A 12:12 roof has no overhang.

  • Level distance = 0 + 24 = 24 inches. Along the slope = 24 x 1.414 = 33.9 inches.
  • The steep-roof rule also requires 36 inches along the slope, and 36 is more than 33.9, so 36 inches controls. One 36-inch roll just does it.

The code measures from the exterior wall line, the outside face of the wall. One maker's instructions measure from the inside wall line instead, which adds the thickness of the wall, so read the instructions for the product you are using. Measure the overhang on the house you are roofing. Deep overhangs on older homes and bump-outs often need two courses, and a guess of "one roll" leaves the wall line unprotected.

Installing Self-Adhering Membrane

  1. Check the conditions. The deck must be clean, dry and free of frost. Many membranes need a deck and air temperature of about 40°F or warmer to stick, and some need a primer on certain decks. Read the roll.
  2. Install the eave drip edge first. The membrane goes on top of the eave drip edge. One maker limits the overhang past the eave edge to 1/4 inch.
  3. Snap a line. Snap a chalk line for the top edge so the roll runs straight. A crooked first course forces wrinkles everywhere above it.
  4. Lay it out, then stick it down. Unroll a manageable length, about 10 to 15 feet, and line it up. Peel back half the release film, press that half down, then peel and press the other half. Work from the center out to push air out.
  5. Lap it right. Upper courses lap over lower ones. End laps run the same direction as water flow and are staggered. Use the lap lines printed on the sheet.
  6. Press it in. Roll or press the whole sheet with firm pressure, especially at laps.
  7. Cover it in time. Most membranes are rated for only a limited time in the sun. Shingle over them before that limit.

Valleys. Center a full-width roll in the valley, starting at the bottom, so each upper piece laps over the lower one. One maker calls for horizontal laps of at least 6 inches and no fasteners within 6 inches of the valley center. Press it into the valley so it does not bridge the crease, because a bridge tears when someone steps on it. The code also sets the valley lining. A closed valley, covered by shingles, can be lined with one ply of 36-inch smooth roll roofing or with self-adhering membrane. An open valley with exposed metal needs metal at least 24 inches wide.

Walls and chimneys. Run membrane at least several inches up the wall behind where the siding or counterflashing will go. One maker calls for at least 5 inches. Do not run felt or synthetic up the sides of a chimney. Use membrane there.

Installing Felt or Synthetic

  1. Start at the eave, over the ice barrier, and roll out parallel to it.
  2. Keep the sheet flat and tight. Felt that gets wet ripples, so let it lie flat or cut and re-lap the wrinkles before shingling.
  3. Lap each course over the one below by the code or the maker's amount, whichever is more.
  4. Lap the underlayment over the top of the ice barrier, never under it. One maker calls for at least 6 inches of lap over the membrane in valleys.
  5. Fasten as the maker requires, and keep nails out of the valley centers.
  6. At the rakes, install drip edge over the underlayment.

Warning: Synthetic underlayment is slippery when it is wet, frosty or dusty, and so is felt on a hot day. Walk on the printed side, keep your fall protection connected, and do not walk on it until dew has burned off.

Common Mistakes

Mistake What it costs
Ice barrier one roll high on a deep overhang Ice dam water gets in above the wall line
Felt lapped under the membrane Water runs off the felt onto bare deck
End laps lined up course after course A water path straight down the roof
Wrinkles left in place Shingles that ripple and do not seal
Membrane bridging the valley A tear and a leak at the worst spot on the roof
Membrane left in the sun too long It loses adhesion and degrades
Staples where the maker requires cap nails Blow-offs and a voided warranty

Check Your Understanding

1. You are roofing a 3:12 shed dormer. Your helper rolls out one layer of synthetic with 4-inch laps. What is wrong?

Slopes from 2:12 up to 4:12 need double coverage: a 19-inch starter strip, then 36-inch sheets lapped 19 inches, unless the code's self-adhering option is used.

2. A 6:12 roof has a 24-inch overhang in an area that requires ice barrier. How far up the slope must the membrane reach?

(24 + 24) x 1.118 = 53.7 inches along the slope. That is two courses of 36-inch membrane.

3. In a valley, a coworker lays felt first and then the self-adhering membrane on top of it. Why is that wrong?

The membrane must be bonded to the deck to seal around nails. It goes first, centered in the valley, and the felt laps over its edges.

4. A shingle maker's instructions call for a 20-inch valley metal, but the code calls for 24 inches for an open metal valley. Which do you use?

The stricter one, 24 inches. Following one rule does not excuse breaking the other.

Key Takeaways

  • Slopes from 2:12 up to 4:12 need two layers. At 4:12 and up, one layer lapped 2 inches.
  • Stagger 4-inch end laps by at least 6 feet.
  • Ice barrier runs from the eave to at least 24 inches inside the wall line, measured level, and to 36 inches along the slope on 8:12 and steeper roofs under the 2021 IRC.
  • Convert the level distance with the slope factor before you decide how many courses to run.
  • Every upper layer laps over the one below, and felt laps over the membrane.
  • Where the code and the maker differ, follow the stricter rule.