Hang wall cabinets on a ledger or jack, fasten them through the rails into studs with cabinet screws, join face frames flush, and keep the whole run level, plumb and flat.

Table of contents

A wall cabinet full of dishes can weigh well over 100 pounds, and it hangs from a few screws over people's heads. That is why wall cabinets are fastened through their hanging rails into framing with real cabinet screws, and why the first cabinet you hang decides how straight the rest of the run will be.

This guide assumes the layout is done: the high point of the floor is found, the level lines are on the wall, and the studs are marked. The cabinet maker's instructions control screw type, spacing and joining method, and they can void the warranty if you ignore them.

What You Will Be Able to Do

  • Choose whether to hang wall cabinets before or after the bases, and set up a ledger or lift.
  • Transfer stud locations to a cabinet and drill the hanging rails.
  • Hang, level and plumb the first cabinet so the run starts true.
  • Clamp and screw face frames flush, and join frameless boxes.
  • Shim behind cabinets so they stay flat on a wall that is not.

Uppers First or Bases First

Many installers hang the wall cabinets first. With no base cabinets in the way, you can stand close to the wall on a stepladder and use a ledger board. Others set the bases first and use a cabinet lift or support blocks on the base tops. Both work. Follow your crew's method and the maker's.

Method Good for Watch for
Uppers first, on a ledger Most kitchens, small crews The ledger must be level and screwed into studs
Uppers first, on a cabinet lift or jack Heavy or tall cabinets Set the lift on a protected, level floor
Bases first, then uppers When base layout sets the uppers' positions Protect the base tops, and do not stand on them

Tools and Fasteners

  • Cabinet screws. One maker supplies #10 x 2-1/2-inch washer-head screws for fastening to the wall and recommends #8 x 2-1/2-inch pan-head or trim-head screws for joining face frames. The broad head bears on the rail without pulling through.
  • Never use drywall screws or nails. Drywall screws are hard and brittle, and they can snap under the sideways load of a loaded cabinet. Nails pull out. Cabinet makers specifically forbid both.
  • Clamps. Two face-frame clamps or bar clamps.
  • Drill bits for pilot holes, sized to the screws.
  • Shims. Tapered wood or composite shims.
  • A ledger. A straight 1x3, 1x4 or 2x2 a little longer than the run.

Set Up a Ledger

A ledger is a temporary board screwed to the wall with its top edge on the wall cabinet bottom line. The cabinets rest on it while you fasten them, so nobody has to hold the weight and drive screws at the same time.

  1. Hold the ledger with its top edge exactly on the line, usually 54 inches above the floor's high point.
  2. Screw it into every stud it crosses.
  3. Check it with a level. Your cabinets will copy any error in it.
  4. Under a window or range hood gap, use a separate short ledger or support block.

The screw holes left by the ledger will be covered by the backsplash. If they will not be, patch them later.

Prepare Each Cabinet

  1. Take off the doors and remove shelves. Label them.
  2. Measure from the corner or from the last cabinet's edge to the center of each stud the cabinet will cover.
  3. Transfer those marks to the inside back of the cabinet, on the top and bottom hanging rails. The hanging rails are the thick strips across the top and bottom of the back, made to take screws.
  4. Drill pilot holes through the rails from inside, on the stud lines. One maker calls for three screws on a 30-inch-tall cabinet and four on 36- and 42-inch cabinets, with holes about 1-3/4 inches from the top and bottom and no closer than 2 inches to a side edge. Follow your maker.
  5. Start the screws in the holes so they are ready when the cabinet goes up.

Hang the First Cabinet

Start at an inside corner, or at the cabinet the layout uses as its starting point.

  1. Lift the cabinet onto the ledger with a helper, and slide it to its marks.
  2. Drive one screw part of the way into a stud through the top rail to hold it.
  3. Check level across the bottom and the top, front to back on the sides, and plumb on the face and the sides.
  4. Shim behind the rails at the studs where the wall is hollow, until the cabinet is plumb and the back is flat.
  5. Drive the remaining screws, but leave them just short of tight so you can nudge the cabinet when you join the next one.

Worked Example: Why the First Cabinet Matters

You hang a 24-inch-wide corner cabinet with its bottom 1/8 inch out of level from one side to the other. That error carries into every cabinet you join to it.

  • 1/8 inch over 2 feet is 1/16 inch per foot.
  • Over an 8-foot run, that adds up to 8 x 1/16 = 1/2 inch.

The last cabinet ends up 1/2 inch above or below the line, and the crown molding, range hood and backsplash all show it. Check the first cabinet three times. It is the cheapest fix you will make all day.

Warning: A wall cabinet is heavy and awkward on a ladder. Lift with a helper, keep the ladder close to the wall, and do not stand on the top two steps of a stepladder. Never stand on a base cabinet or countertop to reach.

Join the Next Cabinet

Face-Frame Cabinets

A face frame is the solid wood frame on the front of the box that the doors hang on. Adjoining face frames are screwed to each other so the run acts as one unit.

  1. Set the next cabinet on the ledger and push it tight to the first.
  2. Line up the face frames at the bottom and front so they are flush, meaning the faces sit in one plane with no lip. Clamp them.
  3. Drill a two-step pilot. One maker uses a 9/64-inch bit through the first stile, then a 1/8-inch bit into the second. The larger hole lets the screw slide through the first frame so it can pull the second one tight.
  4. Drive #8 x 2-1/2-inch screws through the edge of the stile. That maker calls for two screws on 30-inch cabinets and three on taller ones. Put them behind hinge locations where they will not show.
  5. Check the joint with your fingertip. You should not feel a step.
  6. Fasten the cabinet to the studs. Then fully tighten the screws in the previous cabinet.

Work one cabinet at a time: set, clamp, join, check level and plumb, fasten.

Frameless Cabinets

Frameless (European-style) boxes have no face frame. The doors cover the box edges, so the box sides must line up exactly.

  • Join them through the side panels with connector screws or connector bolts, usually through holes the maker has drilled.
  • Line up the front edges and the bottoms before you tighten.
  • Gaps between doors on frameless cabinets are small and very visible, so a box out of line by 1/16 inch shows.

Keep the Back Flat

Proper tightness means drawing a screw down until the rail just touches the wall or the shim behind it. If you keep driving the screw into a hollow wall, it pulls the back in, the box twists, and the doors stop lining up.

  • Shim at every screw where there is a gap behind the rail.
  • Lay a level across the faces of the run. It shows where the run is bowing in or out.
  • Check doors by hanging one or two as you go. A door that will not line up with its neighbor often means a twisted box, not a bad hinge.

Fillers, Ends and Special Cabinets

  • Fillers at walls. A filler between the last cabinet and a wall is scribed to the wall, so it fits tight even if the wall is not plumb. Screw it to the face frame from inside before or after the cabinet goes up, as the layout calls for.
  • End panels. An exposed side gets a finished end panel. Fasten it from inside the cabinet with screws short enough that they cannot come through the face.
  • Over the range. Set the cabinet over the cooktop at the height the hood or microwave instructions call for, and leave the opening it needs. The International Residential Code calls for at least 30 inches from the cooktop to unprotected combustible material unless a listed hood or appliance allows less. Installing the hood or microwave is a separate job, and its wiring and venting may need a licensed electrician or mechanical permit.
  • Over the refrigerator. These deep, short cabinets often need a support block or a tie-in to a tall cabinet or panel. Check the refrigerator's height and air gap first.
  • Tall cabinets. Pantry and oven cabinets must line up with both the base line and the wall cabinet tops. Fasten them to studs and to the cabinets beside them.
  • Lighting. Under-cabinet light wiring comes out of the wall where the electrician roughed it in. Do not cut or splice it yourself.

Final Checks

  1. Every cabinet is fastened into framing with the screws the maker specifies.
  2. Bottoms are level along the run, and faces are plumb and flush.
  3. Doors hang with even gaps.
  4. The ledger comes off, and its screw holes will be covered or patched.
  5. Any screw that missed a stud is pulled and moved. A missed screw holds nothing.

Fixing Problems

Symptom Likely cause Fix
Doors on one cabinet will not line up Box twisted by a hollow wall Loosen, shim behind the rail, retighten
Step between face frames Frames not clamped flush before screwing Back out the screws, clamp, redrive
Run drifts off the line First cabinet out of level Reset the first cabinet
Gap at the top behind the cabinet Wall leans in at the top Shim behind the top rail at the studs
Cabinet moves when pushed Screws in drywall only, or missed studs Find the studs and refasten

Check Your Understanding

1. A helper wants to hang the uppers with coarse drywall screws because they are what is on the truck. What do you tell them?

No. Drywall screws are brittle and can snap under the load of a full cabinet. Use the cabinet screws the maker specifies, such as #10 washer-head screws into studs.

2. You tighten a cabinet's screws and the doors stop meeting evenly. What happened?

The screws pulled the back into a hollow in the wall and twisted the box. Back the screws off, shim behind the rail at the studs, and tighten until the rail just touches the shim.

3. Your first 30-inch cabinet is 1/16 inch out of level across its width. How far off will a 10-foot run be?

1/16 inch over 2.5 feet is 1/40 inch per foot, so about 1/4 inch over 10 feet. Fix the first cabinet before going on.

4. Two face frames have a slight lip between them after you screw them together. What went wrong, and how do you fix it?

They were not clamped flush first. Remove the screws, clamp the faces flush, and drive the screws again.

Key Takeaways

  • Hang wall cabinets on a level ledger or lift, never by holding them and driving screws.
  • Fasten through the hanging rails into studs with cabinet screws, not drywall screws or nails.
  • Get the first cabinet level and plumb, since every error grows down the run.
  • Clamp face frames flush before screwing them together.
  • Shim behind the rails so the box stays flat and the doors line up.