Laying Out Siding Courses

15 min read Training Guide

Set a level starting line around a house, build a story pole, and work out a course exposure that lands lap siding cleanly at window sills and heads.

Table of contents

On a well-sided house the courses run dead level around every corner, and each window looks like it was built to fit the siding. That does not happen by luck. Before the first board goes up, someone measures the walls, marks the key heights on a stick, and does a little division so the courses land where the eye looks. Skip that step and you get thin slivers under windows, notched boards that leak, and courses that drift a half inch uphill by the time they reach the far corner.

This guide covers layout for lap siding: wood, fiber cement, engineered wood and vinyl. The math is simple. The discipline is in checking it.

What You Will Be Able to Do

  • Find the lowest point of a wall and set a level starting line all the way around the house.
  • Build and mark a story pole with every height that matters.
  • Work out a course exposure that fits a product's lap limits and lands at sills and heads.
  • Transfer the layout to corners and openings and keep courses level as you go up.
  • Plan butt joints so they do not stack up.

Terms

  • Course: one row of siding.
  • Exposure: how much of each board shows, measured from the bottom edge of one course to the bottom edge of the next. Also called the reveal.
  • Lap or overlap: how much each course covers the one below it. Board width minus exposure equals lap.
  • Butt line: the bottom edge of a course.
  • Story pole: a straight stick marked with the heights of everything on a wall, used to lay out courses without measuring each one.
  • Starting line: the level line where the bottom of the first course sits.

The Limits You Work Within

Every product has a minimum lap, and that sets the largest exposure you can use. You can shrink the exposure to make courses fit, but you cannot stretch it past that limit.

Product Exposure Rule that sets it
Vinyl lap siding Fixed by the panel Panels lock together, so exposure cannot change
Fiber cement lap Adjustable within limits One major maker requires at least 1-1/4 inch of lap
Engineered wood lap Adjustable within limits One major maker requires at least 1 inch of lap
Wood bevel siding Adjustable within limits The wood siding association calls for at least 1 inch, more on wide boards

Example: an 8-1/4-inch fiber cement plank with a 1-1/4-inch minimum lap can show no more than 8-1/4 minus 1-1/4, or 7 inches. You can lay it at 6-1/2 inches to make courses fit, but never at 7-1/2.

Clearances set the bottom of the wall. Fiber cement and engineered wood makers commonly require 6 inches above finished grade and 1 inch or more above roofs, decks and walkways. Vinyl J-channel along a roof stays at least 1/2 inch above the roofing. Check the instructions for your product before you pick a starting height.

Step 1: Set a Level Starting Line

Foundations are rarely level, and the ground never is. The siding must be level anyway, or the courses will run downhill and every window will look crooked.

  1. Find the lowest point. With a laser level or a builder's level, check the top of the foundation or the bottom of the sheathing all the way around the house. Mark the lowest spot.
  2. Check the clearance there. At that low spot, the bottom of the first course must still meet the maker's clearance to grade. If the grade is too high, the grade needs fixing before siding goes on, not the siding.
  3. Mark the starting height. At the lowest point, mark where the bottom edge of the first course will be. For vinyl, the chalk line goes 1/4 inch less than the starter strip's width above the lowest point, per the vinyl siding installation manual.
  4. Carry it around the house. Shoot that same height onto every corner and every few feet along each wall with the laser. Snap chalk lines between the marks.
  5. Close the loop. When you get back to where you started, the line should meet itself. If it is off, find the mistake now. A line that misses by 1/2 inch at the last corner leaves a visible step in the siding.

A water level, which is a clear hose filled with water, works without batteries and is accurate over long distances. Water finds the same height at both ends.

Step 2: Build a Story Pole

Use a straight 1x2 or 1x3 a little longer than the wall is tall. Hold it plumb with its bottom on the starting line, and mark:

  • The starting line.
  • The bottom of each window sill or sill trim.
  • The top of each window and door head flashing or drip cap.
  • The bottom of the soffit, frieze board or any trim band.
  • Anything else the siding must meet, such as a porch roof, a deck ledger flashing or a change in material.

Label each mark. If windows on different walls sit at different heights, make a separate pole for each wall or mark each set in a different color.

Step 3: Do the Math

The goal is to have a course's bottom edge land at the bottom of each sill and at the top of each head flashing. Then the boards meet the windows at full width, with no slivers and no notches across the top of a window.

For each zone between two marks:

  1. Measure the zone. Read the distance off the story pole.
  2. Divide by the largest allowed exposure. The answer is the fewest courses that fit.
  3. Round up to a whole number of courses.
  4. Divide the zone by that number. The answer is the exposure for that zone. It will always be at or under the limit.

Worked Example

You are laying out 8-1/4-inch fiber cement plank, so the largest exposure is 7 inches. The story pole reads:

  • Starting line to the bottom of the window sill: 37-1/2 inches.
  • Bottom of the sill to the top of the head flashing: 52 inches.
  • Top of the head flashing to the bottom of the frieze board: 19-1/2 inches.
Zone Divide by 7 Courses Exposure
Start to sill 37.5 / 7 = 5.36 6 37.5 / 6 = 6-1/4 inches
Sill to head 52 / 7 = 7.43 8 52 / 8 = 6-1/2 inches
Head to frieze 19.5 / 7 = 2.79 3 19.5 / 3 = 6-1/2 inches

The wall takes 17 courses. The exposures differ by only 1/4 inch between the bottom zone and the rest, which no one will notice from the yard. If one zone had come out 1 inch smaller than its neighbor, that jump would show.

When the Numbers Do Not Work

  • Big difference between zones. Choose the window zone first, since that is where people look. Then let the top course rip narrower where trim or a frieze board hides it.
  • Windows at different heights. Lay out for the windows on the front wall or the wall people see most. On other walls, accept a ripped piece at a sill or head, and use trim to make it look planned.
  • Vinyl siding. Exposure is fixed, so you cannot make courses land on windows. Instead, plan cuts. Panels cut under a sill or at the top of a wall lock into utility trim using a snap lock punch. Adjust the starting height a little, within the clearance limits, to avoid a very thin strip at the top of the wall, which is hard to fasten and looks like a mistake.

Step 4: Transfer the Layout

  1. Mark the corners. Hold the story pole against each corner board or corner post and transfer every course mark. Do the same on each window's trim, both sides.
  2. Snap lines where you need them. Some crews snap a line for every course. Others snap one every few courses and use siding gauges in between.
  3. Use siding gauges on adjustable products. Gauges are clamps that hook the course below and hold the next board at the set exposure. They let one person set long planks. Check that the gauge is set to the exposure for that zone, and reset it when you move to the next zone.
  4. Mark the stud lines. Snap vertical lines on the WRB at each stud, since most lap siding is nailed into framing.

Step 5: Keep It Level as You Go

  • Check often. The vinyl siding manual says to check alignment every fifth or sixth course. That is a good habit on any lap siding.
  • Measure down from the top. Every few courses, measure from the soffit or frieze down to the last course at both ends of the wall. The numbers should match.
  • Check the corners. Courses must line up across a corner. A course that is 1/4 inch off at a corner is easy to see.
  • Fix drift early. Correct a small error over two or three courses by changing exposure a hair at a time. A sudden fix in one course is visible.

Planning Butt Joints

A butt joint is where two boards meet end to end in the same course. Joints that stack in a line up the wall look bad and leak more.

  • Vinyl: keep seams at least 2 feet apart from one course to the next, with at least three courses between seams that line up, per the vinyl siding manual. Lap panels away from entrances and the spots where people look most.
  • Fiber cement and engineered wood: stagger joints, and treat each one the way the maker requires, such as joint flashing behind it, sealant, or a joint cover.
  • Wood: land joints on studs and stagger them.
  • Use long boards. Plan each course so it uses full lengths where possible and short pieces only where they are hidden.

Common Mistakes

Mistake What it costs
Starting from the foundation top without checking level Courses run uphill, and windows look crooked
Exposure larger than the minimum lap allows Water gets behind the siding, and the warranty is void
No story pole Slivers and notches at every window
Not closing the level loop around the house A step where the last wall meets the first
Forgetting the grade or roof clearance Siding wicks water and rots or swells
Joints stacked in a line A visible seam up the wall and more leak paths
Checking level only at the end Drift too big to fix without tearing off courses

Check Your Understanding

1. You are installing 9-1/4-inch fiber cement plank with a 1-1/4-inch minimum lap. What is the largest exposure you can use?

9-1/4 minus 1-1/4 equals 8 inches. You can use less than 8 to make courses fit, but never more.

2. The zone from the sill to the head flashing is 58 inches, and your largest exposure is 7 inches. How many courses, and at what exposure?

58 / 7 = 8.29, so round up to 9 courses. 58 / 9 = 6.44 inches, which is a little over 6-7/16 inches.

3. You shoot a level line around a house and come back to the first corner 3/8 inch high. What do you do?

Stop and find the error before any siding goes up. Re-shoot from the low point, check each wall's marks, and snap new lines that close.

4. On a vinyl job the top course under the soffit would be a 1-inch strip. What can you do?

Vinyl exposure is fixed, so adjust the starting height slightly within the clearance limits, or plan a wider trim at the top, so the last piece is a usable width that locks into utility trim.

Key Takeaways

  • The minimum lap sets the largest exposure. You may shrink it to fit, never stretch it.
  • Start from a level line set at the lowest point, and make sure it closes around the house.
  • A story pole holds every height that matters, so layout is marked once and transferred.
  • Divide each zone by the largest exposure, round up, and divide again.
  • Vinyl has a fixed exposure, so plan cuts instead of courses.
  • Check level and spacing every few courses, and stagger butt joints.