Planning and Running a Small Project
Write a one-page scope, break the work into tasks with owners and estimates, find the chain of tasks that sets the end date, send weekly status updates, and control changes until the project closes.
Table of contents
Sooner or later, your manager will hand you something that is not part of the daily routine: set up a new pickup area, move the stockroom, roll out new software, remodel the break room, open on Sundays, get ready for an audit. That is a project: one-time work with a goal, a deadline and an end. Projects fail for ordinary reasons. Nobody wrote down what "done" means, two people each thought the other had a task, or a delay no one mentioned until the week it was due. A one-page plan and a weekly update prevent most of that.
What You Will Be Able to Do
- Write a one-page scope that says what the project will and will not do.
- Break the work into tasks, each with one owner and an estimate.
- Put tasks in order, and find the chain of tasks that sets the earliest finish.
- Send a short weekly status update with honest colors.
- Handle change requests and close the project out.
Is It a Project?
| Routine work | Project |
|---|---|
| Happens every day or week | Happens once |
| Has no end date | Has a deadline and a finish |
| Run by a written procedure | Needs a plan |
| Example: weekly ordering | Example: switching to a new supplier system |
Some projects are a weekend of work. Others take months and involve other departments, outside vendors and the budget. The steps below scale to both. A small one may need a page. A bigger one needs every part.
Write a One-Page Scope
Before anyone starts, write down what the project is. Some companies call this a project charter. Get your sponsor, the person who asked for it and can approve changes, to agree to it.
The example used below is a unit switching 40 employees from paper time cards to a new scheduling and time clock app.
| Part | Example |
|---|---|
| Goal | All 40 employees schedule and clock in on the new app |
| Why | Paper time cards cause pay errors and take hours to total |
| Done means | One full pay period on the app with totals that match the old system |
| In scope | Setup, wall clocks, testing, training, one side-by-side pay period |
| Out of scope | Changing pay rules, other locations |
| Deadline | The paper system's service contract ends after week 10 |
| Budget | Set by the approved quote |
| Sponsor | The general manager |
| Project lead | You |
Out of scope matters as much as in scope. It is the line that stops a three-week project from turning into a three-month one.
Break the Work Into Tasks
List everything that has to happen. Ask the people who will do the work, because they know steps you will miss. For each task:
- Name it with a verb and a thing: "Install wall clocks," not "Clocks."
- Keep it small enough to estimate, from a day to about two weeks. Split anything bigger.
- Give it one owner. "The team" owns nothing. One name per task.
- Say what it produces, so everyone knows when it is done.
Estimate How Long
Ask the owner how long each task will take, in working days. For tasks with real uncertainty, use a three-point estimate:
Estimate = (best case + 4 x most likely + worst case) / 6.
Worked example. The payroll lead says loading the employee list and pay rules could take 5 days if everything goes right, most likely 7, and 15 if the data is messy.
- 4 x 7 = 28.
- 5 + 28 + 15 = 48.
- 48 / 6 = 8 working days.
The worst case pulls the estimate up from 7 to 8. That is the point: it builds in some of the risk instead of planning on everything going right.
Put the Tasks in Order
Some tasks cannot start until another one finishes. Write down what each task comes after.
| Task | Owner | Days | Comes after |
|---|---|---|---|
| A. Sign contract, order clocks | Purchasing | 5 | Start |
| B. Load employees and pay rules | Payroll lead | 8 | A |
| C. Install wall clocks | Facilities | 4 | A |
| D. Set up positions and schedules | You | 6 | B |
| E. Test with 6 employees for one pay period | You | 10 | C and D |
| F. Train all employees | Shift leads | 5 | E |
| G. Go live, run old and new side by side | You and payroll | 10 | F |
If installing the clocks needs new outlets or wiring, that part is work for a licensed electrician. Facilities arranges it.
Find the Chain That Sets the Date
Follow each path from start to finish and add the days:
- A, B, D, E, F, G: 5 + 8 + 6 + 10 + 5 + 10 = 44 working days.
- A, C, E, F, G: 5 + 4 + 10 + 5 + 10 = 34 working days.
The longest chain, 44 days, is the critical path. It sets the earliest the project can finish. Any delay on a task on that chain moves the end date by the same amount.
Task C is not on the critical path. It can finish by day 9, but testing cannot start until D finishes on day 19. So C has 10 days of slack: it can slip up to 10 days without moving the end date.
At 5 working days a week, 44 days ends in week 9. The deadline is the end of week 10, or 50 working days. That leaves 6 days of cushion. Protect it. Cushion gets used up by things nobody planned.
When the Date Does Not Fit
If the critical path runs past the deadline, only changes to tasks on that chain help:
- Overlap tasks, such as training the first group while testing finishes. This adds risk, so say so.
- Add help to a critical task, if more people really make it go faster.
- Cut scope, with the sponsor's agreement.
- Move the date, which is the sponsor's call, not yours.
Speeding up task C does nothing for the end date, because it already has slack.
Owners and Who to Keep Informed
For each task, know who does it, who approves it, who must be asked first, and who just needs to be told. Some companies call this a RACI chart: responsible, accountable, consulted, informed. In the example, payroll must be consulted before any pay setting changes, and every employee must be told before go-live.
List the Risks
A risk is something that might go wrong. Write each one down with a plan, before it happens.
| Risk | How likely | How bad | Plan |
|---|---|---|---|
| Clocks arrive late | Medium | Low, C has slack | Order in week 1, confirm the ship date |
| Pay rules set up wrong | Medium | High, wrong paychecks | Compare app totals with paper totals before payday |
| Staff miss training | High | Medium | Three session times, one makeup session, sign-in sheet |
| Vendor setup slips | Low | High, on the critical path | Weekly vendor call, raise it the day it slips |
Look at the list every week. Close risks that have passed, and add new ones.
Send a Weekly Status Update
Send it on the same day each week, to the same people, in the same shape. Keep it short enough to read in a minute.
- Overall: green, yellow or red.
- Done this week: tasks finished.
- Next week: tasks starting or finishing.
- Risks and issues: what might slip or has slipped, and the plan.
- Decisions needed: what, from whom, and by when.
Define the colors and use them honestly:
| Color | Means |
|---|---|
| Green | On track for the date and budget |
| Yellow | At risk, with a plan to recover |
| Red | Will miss the date or budget without a decision from the sponsor |
A project that is green every week until it is suddenly red has not been reported honestly. Yellow early is how a sponsor gets the chance to help.
Example update, week 3: Overall yellow. Done: contract signed, clocks ordered, employee list loaded. Next: pay rules finished by Wednesday, position setup starts Thursday. Issue: the vendor has not confirmed a date for the pay rule review, and task B is on the critical path. Plan: call their manager Monday. Decision needed: none this week.
Track project spending against the approved budget as you go, and include it in the update when anything changes.
Handle Changes
Once work starts, people will ask for more. That is called scope creep, and it is how projects run late without anyone deciding they should. Handle every change the same way:
- Write down what is being asked and why.
- Figure the effect on time and cost.
- Take it to the sponsor, who decides.
- If approved, update the scope, the task list and the dates, and tell the team.
Worked example. In week 4, the general manager asks you to also set up break tracking in the app. It adds 3 days to task D. D is on the critical path, so the end date moves from day 44 to day 47, and the cushion drops from 6 days to 3. Put that in front of the sponsor before you say yes.
Close It Out
- Check the "done means" line from the scope. Is it true?
- Finish the punch list of small open items, each with an owner.
- Hand the work over to whoever owns it from now on, with any new procedures written down.
- Close out the budget and report the final cost.
- Hold a short review: what went well, what to do differently next time. Write it down.
- Thank the people who did the work, by name.
Common Mistakes
| Mistake | What it costs |
|---|---|
| No written scope | Everyone has a different idea of done |
| Tasks owned by "the team" | Nobody does them |
| Estimates nobody checked with the doer | Dates that were never possible |
| Speeding up tasks that are not on the critical path | Effort that does not move the end date |
| Green status until the last week | No time left to recover |
| Saying yes to every change | The project runs late and over budget |
| Skipping the handoff | The new system drifts back to the old way |
Check Your Understanding
1. A task could take 2 days at best, 4 most likely, and 12 at worst. What is the three-point estimate?
(2 + 4 x 4 + 12) / 6 = (2 + 16 + 12) / 6 = 30 / 6 = 5 days.
2. Task A takes 3 days. B takes 5 days and C takes 2, and both start after A. D takes 4 days and starts after both B and C. What is the critical path, and how much slack does C have?
A, B, D is 3 + 5 + 4 = 12 days. A, C, D is 3 + 2 + 4 = 9 days. The critical path is A, B, D, and C has 12 - 9 = 3 days of slack.
3. In that same project, C slips 2 days. Does the end date move? What if it slips 4 days?
A 2-day slip does not move it, because C has 3 days of slack. A 4-day slip uses up the slack and moves the end date by 1 day.
4. Halfway through, a department head asks you to add a second location to the rollout. What do you do?
Write down the request, figure what it adds in time and cost, and take it to your sponsor. Do not agree to it on the spot.
5. Every task is on schedule, but the vendor has not confirmed a date for a setup step that is on the critical path. What color is your status?
Yellow. Nothing has slipped yet, but a critical-path task is at risk. Say so, and give your plan to get the date confirmed.
Key Takeaways
- Write a one-page scope with a clear "done means" line and an out-of-scope list, and get the sponsor to agree.
- Give every task a verb, one owner and an estimate from the person doing it.
- The longest chain of dependent tasks is the critical path. Only changes on that chain move the end date.
- Keep a risk list with a plan for each risk, and look at it every week.
- Send a short weekly update with honest colors, and take every change to the sponsor with its cost in time and money.
- Close out with a handoff, a final cost and a short review.