Roof Tear-Off and Deck Repair

15 min read Training Guide

Decide between tear-off and recover, set up a safe drop zone, strip a roof down to the deck, repair bad sheathing, and dry the roof in before the weather turns.

Table of contents

Tear-off day is the day a house is most exposed. The old roof is gone, the new one is not on yet, and one afternoon storm can soak the attic, the insulation and the ceilings below. It is also the dirtiest and most dangerous day of the job: loose granules roll like ball bearings, nails point up everywhere, and debris falls two stories. A good tear-off is planned so the crew never opens more roof than it can close the same day.

This guide covers steep-slope residential reroofing down to a wood deck. The local building department, the adopted code edition, the plans and the shingle maker's instructions control the details. Before anyone goes up, your employer must have fall protection in place. In residential construction, OSHA requires guardrails, safety nets or personal fall arrest at 6 feet or more above a lower level (29 CFR 1926.501(b)(13)).

What You Will Be Able to Do

  • Decide whether code allows a roof to be covered over or whether it must come off.
  • Set up the site so debris, people, cars and plants stay safe.
  • Strip a roof in the right order and leave a clean deck.
  • Find and repair bad sheathing, and know when damage needs someone else's decision.
  • Dry a roof in so it can survive a storm overnight.

Tear-Off or Recover

A roof replacement removes every layer down to the deck. A recover puts new roofing over the old. The 2021 International Residential Code (IRC) Section R908 sets the limits, and many towns and shingle makers are stricter.

Existing roof Recover allowed?
One layer, dry and sound Often, if the new roofing maker allows it
Two or more layers of any kind No, tear off
Water-soaked or deteriorated No, tear off
Slate, clay, cement or asbestos-cement tile No

One exception helps on many reroofs: an ice barrier membrane that is stuck to the deck may stay in place, as long as a new layer of ice barrier goes over it. A shingle laid on top of old shingles telegraphs every bump and hides deck damage, so most crews tear off even when a recover is allowed.

Count the layers before you bid. Look at the rake edge, lift a shingle at a vent pipe, or check from the attic for long nails poking through. Each layer adds weight and labor, and the dumpster size changes with it.

Hazards to Check First

  1. Asbestos. The EPA lists roofing and siding shingles among products that may contain asbestos, and asbestos-cement shingles look like hard, flat, slate-like panels. Felt and mastics on very old roofs can also contain it. You cannot tell by looking. If the roof is old and nobody knows what it is, stop and have it tested before tear-off.
  2. Lead. Old pipe boots and some flashings are lead. Wear gloves, keep it out of your mouth, and wash before you eat.
  3. Power lines. Note the service drop and any lines near the roof edge. Metal flashing, drip edge and ladders all conduct.
  4. Weather. Read the hourly forecast, not just the daily one. Wind over a light breeze makes tarps and underlayment dangerous to handle.
  5. The attic. Nails and dust will fall through gaps in board decks. Ask the owner to cover anything stored in the attic.

Setting Up the Site

Debris control decides how clean and safe the day goes.

  • Dumpster. Place it under an eave you can reach without carrying debris across the roof. Protect the driveway with plywood under the dumpster if the owner asks.
  • Chutes and drop zones. OSHA requires an enclosed chute when material is dropped more than 20 feet to a point outside the building's walls (1926.252(a)). For lower drops, rope off the landing area and keep people out of it while debris is coming down.
  • Protection. Lay tarps over plants, decks and patios. Lean plywood over windows and AC units under the drop area. Move cars.
  • Magnets. Keep a rolling magnet on site from the first hour, not just at the end.

Tearing Off

Work one section at a time, and only as much as the crew can dry in that day.

  1. Start at the top. Pull the ridge caps and hip caps first, then any ridge vent.
  2. Strip downhill. Slide a tear-off shovel or fork under the shingles from the ridge down, prying up shingles and nails together. Let the debris slide down onto a tarp or into the chute. Never throw debris over the edge without checking below.
  3. Remove old flashing. Pull step flashing, pipe boots and vents. The code requires flashings to be rebuilt to the new maker's instructions and rusted or damaged parts replaced, so plan on new metal.
  4. Clear the felt. Scrape off old underlayment. If an adhered ice barrier is staying, leave it, and plan a new layer over it.
  5. Pull or drive every nail. A nail head left standing will punch through new underlayment and lift a shingle. Run your hand or a flat bar across the deck to find them.
  6. Sweep. A clean deck shows you every soft spot, gap and rotted edge.

Warning: A stripped deck covered in granules is slicker than shingles. Stay tied off, set roof jacks and toe boards as you go, and clear debris from your footing before you step.

Inspecting the Deck

Walk the deck slowly with your eyes down. Press with your boot near every rafter bay.

What you find Likely cause What to do
Soft or spongy spot Rot from a long leak Cut out and replace the panel section
Dark stains around a vent or chimney Old flashing leak Probe it, replace if soft
Swollen or crumbling OSB edges Edges got wet repeatedly Replace the damaged strip
Peeling plywood layers Delamination from moisture Replace the panel
Sagging between rafters Thin or soaked panels Replace, check the span rating
Gaps wider than about 1/8 inch in board decks Shrinkage or spaced sheathing Cover the whole deck with new panels
Cracked, split or sagging rafter Overload, rot or a cut by a past trade Stop and report it

Board decks. Asphalt shingles must be fastened to a solid deck (IRC R905.2.1). One major shingle maker accepts board decks only when the boards are at least 1-inch nominal thickness, no wider than 6 inches, and spaced no more than 1/8 inch apart. Spaced boards left from an old wood shake roof do not qualify. They need new plywood or OSB laid over the whole roof.

Structure is not your call. Replacing sheathing is normal reroof work. Sistering, cutting or repairing a rafter or truss is structural work. Photograph it, mark it, and tell your lead so the builder or an engineer can decide the fix.

Replacing Bad Sheathing

Use new panels the same thickness as the existing deck so the new roof lies flat. Check the span rating stamped on the panel. A rating such as 24/16 means it can span up to 24 inches between roof supports, so it must match or beat the rafter or truss spacing.

  1. Find the supports. Mark the rafters or trusses on both sides of the bad area. Panel edges must land on the center of a support.
  2. Cut it out. Set a circular saw to the deck thickness so you do not cut into the rafters. Cut along the center of the supports, or just beside them and add a nailer.
  3. Check the edges. Long panel edges that do not land on a support need edge clips or blocking, as the panel's rating requires.
  4. Gap the new piece. The APA, the wood panel trade association, recommends about 1/8 inch at panel ends and edges so the wood can swell without buckling.
  5. Fasten it. Follow the nailing schedule on the plans or in the adopted code. High-wind areas call for closer spacing near the edges and corners of the roof, so check before you nail.

Worked Example: Patching Below a Chimney

The deck is soft in an area about 3 feet wide and 3 feet tall below a chimney. The trusses are 24 inches on center, and the existing panels run across the trusses in 4-foot-tall courses.

  • A 3-foot-wide cut would end between trusses. Widen it to 4 feet so both side edges land on truss centers.
  • Move the top and bottom cuts to the panel joints above and below the soft area. The patch is then the full height of that course, and its top and bottom edges meet existing joints. If the soft area crosses a joint, replace both courses.
  • Cut a 4 x 8 sheet in half to get a 4 x 4 piece. Keep the sheet's long direction running across the trusses, the same as the panels around it, because a panel is stiffer along its length.
  • Add edge clips at the top and bottom edges if the old panels had them, leave 1/8 inch at each edge, and fasten to the schedule.

Drying In

Dry-in means getting the deck covered with underlayment so rain cannot reach it. Underlayment is not a finished roof, but it will keep most water out for a short time.

  1. Install eave drip edge, ice barrier and underlayment on each section you strip, the same day.
  2. If you cannot finish a section, cover the open deck with a heavy tarp that runs over the ridge onto the other side, so water cannot run under its top edge.
  3. Hold the tarp with wood battens fastened through the tarp edge, not with bricks or loose boards that will slide off in wind.
  4. Check the tarp and underlayment before you leave and again after any storm.

Cleaning Up

  • Roll the magnet over the yard, driveway, beds and street twice: once at the end of tear-off, once at the end of the job.
  • Clean granules, nails and shingle scraps out of the gutters.
  • Bag lead and any tested asbestos waste as your employer and local rules require. Regular debris goes in the dumpster.

Common Mistakes

Mistake What it costs
Opening the whole roof at once A soaked house when the storm comes early
Leaving nail heads on the deck Torn underlayment and lifted shingles
Covering soft decking A new roof with a sag and a nail that will not hold
Tearing off untested old material Asbestos exposure and a contaminated site
Dropping debris without a chute or a barricade A struck coworker or a damaged car
Fixing a cracked rafter yourself A structural problem nobody signed off on

Check Your Understanding

1. The roof has three-tab shingles over an older layer of wood shingles. The owner wants new shingles laid on top. What do you tell your lead?

Code does not allow a recover over two or more existing layers. Both layers come off, and the spaced boards under the wood shingles will need new sheathing.

2. Rain is forecast for 3 p.m. The crew can strip and dry in about half the roof by then. What is the plan?

Strip and dry in one slope at a time. Finish the first slope completely before opening the second, and stop opening new deck when you cannot close it before the rain.

3. You find a rafter with a deep notch cut by an old plumbing vent. What do you do?

Stop work in that area, photograph and mark it, and report it. Rafter repair is a structural decision for the builder or an engineer.

4. A new piece of OSB fits tightly against the old deck on all sides. Why is that a problem?

Wood panels swell with moisture. With no gap, the edges can buckle and show through the shingles. Leave about 1/8 inch.

Key Takeaways

  • Open only as much roof as the crew can dry in the same day.
  • Two or more existing layers, or a wet or rotted roof, means a full tear-off.
  • Test old roofing of unknown age for asbestos before you tear it off.
  • Pull or drive every old nail and sweep the deck before you inspect it.
  • Patch sheathing with the same thickness, edges on supports, and a 1/8-inch gap.
  • Report damaged rafters and trusses. Do not repair structure yourself.