Roofing Installation

20 min read Training Guide

Lay an asphalt shingle roof in the right order, from deck check through drip edge, underlayment, shingles, valleys, flashing, ridge cap and ventilation.

Table of contents

A roof works like the feathers on a bird. Each layer overlaps the one below, so water runs from piece to piece until it falls off the edge. Almost every leak comes from a place where that order was broken: a flashing tucked the wrong way, a nail in the wrong spot, a shingle cut short in a valley. Learn the order, and most of roofing makes sense.

This guide covers steep-slope asphalt shingles, which are the most common US residential roof. The shingle maker's instructions, the local code and the plans all control the details, and following the maker's instructions keeps the warranty valid. Before you go up, your employer must have a fall protection plan in place. Fall protection is required at 6 feet or more, and any anchor must be rated for 5,000 pounds per worker or designed by a qualified person.

What You Will Be Able to Do

  • Name the parts of a roof and explain how each one sheds water.
  • Figure squares, bundles and roof load.
  • Install drip edge, ice barrier and underlayment in the right order.
  • Nail shingles correctly, and build valleys and flashing that do not leak.
  • Explain how balanced ventilation works.

Roof Terms

Term Meaning
Eave Lower edge of the roof
Rake Sloped edge at a gable end
Ridge Peak where two slopes meet
Hip Outside corner where two slopes meet
Valley Inside corner where two slopes meet
Slope Rise per 12 inches of run, written 6/12 or 6:12
Square 100 square feet of roof
Exposure Part of a shingle left showing

Materials

Shingles

Three-tab shingles are a single layer with cutouts and a 5-inch exposure. Architectural (dimensional or laminated) shingles have two or more layers, weigh more, resist wind better, and are the standard on most new roofs. Their exposure is commonly 5-5/8 inches.

A square of architectural shingles typically weighs 250 to 350 pounds. Three-tab is lighter, and premium shingles are heavier. Bundles usually weigh 60 to 80 pounds, with three bundles per square for most products.

The recommended minimum slope for standard shingle installation is 4/12. The code and many manufacturers allow shingles down to 2/12 with a double layer of underlayment or a special low-slope method. Below that, shingles will not shed water, and a membrane or other low-slope system is needed.

Underlayment and Ice Barrier

Underlayment covers the deck and is the backup layer. Asphalt felt comes in 15- and 30-pound grades. Synthetic underlayment is lighter, stronger and lies flatter.

Ice and water shield is a self-adhering waterproof membrane that seals around nails. It is used at eaves, valleys and penetrations. In places with a history of ice dams, the International Residential Code (IRC) requires it at the eaves, running from the lowest edge of the roof to at least 24 inches inside the exterior wall line. On roofs of 8:12 and steeper, the 2021 IRC also requires at least 36 inches measured along the slope from the eave edge, and code editions differ on this line. The local building department decides whether your area needs it, and some areas ask for more. Many products need a surface above about 40°F to stick, so check the label.

Metal and Nails

Drip edge directs water away from the fascia, prevents wicking under the shingles, and protects the deck edge. It overlaps 2 inches at joints and is nailed about every 12 inches.

Roofing nails are corrosion-resistant with at least a 12-gauge shank and 3/8-inch head. They must go at least 3/4 inch into the deck or through it. Coil nailers are standard on crews. Nail gun rules apply here: keep your finger off the trigger when you move, and use a full sequential trigger unless your employer tells you otherwise.

Figuring Material

Roof area is larger than the floor area below it. Multiply the flat area by a slope factor.

Slope Factor
4/12 1.054
6/12 1.118
8/12 1.202
10/12 1.302
12/12 1.414

Worked example. A simple gable roof covers 30 feet by 40 feet (including overhangs) at 6/12.

  • Flat area = 30 x 40 = 1,200 square feet.
  • Roof area = 1,200 x 1.118 = 1,342 square feet = 13.4 squares.
  • Add 10 percent for waste and starters: about 15 squares.
  • Bundles = 15 x 3 = 45.
  • Weight at 300 pounds per square = 4,500 pounds.

Spread that weight out on the roof. Do not pile bundles in one spot.

Installation Order

1. Check the Deck

Look for soft spots, rot and protruding nails. Replace bad sheathing and make sure the panel edges are supported. On a reroof, this is the moment to catch damage. Check the forecast before you tear off, and keep tarps ready. Very old roofing materials can contain asbestos, so ask before you tear off a roof of unknown age.

2. Drip Edge at the Eaves

Nail drip edge to the deck at the eaves. Going in first, on the deck, under the underlayment, it lets water that runs down the underlayment fall onto it.

3. Ice Barrier

Where required, press the membrane to the deck and over the eave drip edge. Lap seams as the maker specifies. Apply it in valleys and around penetrations.

4. Underlayment

Roll it out from the eave up, lapping each course over the one below. Follow the maker's lap and fastener instructions, which vary by product. Wrinkles show through shingles, so keep it flat.

5. Drip Edge at the Rakes

At the rakes, the drip edge goes over the underlayment. So the rule is: under the underlayment at the eave, over the underlayment at the rake. In both cases, water coming down the roof lands on top of the next layer.

6. Starter Strip

The starter strip goes along the eave so that the first course has sealant under it and the tab cutouts do not expose the deck. It seals the first course down, blocks wind-driven rain, and improves wind resistance at the edge. Use a manufactured starter or cut shingles, with the sealant near the eave. Offset its joints from the first course.

7. Field Shingles

Work from the eave up, with chalk lines every few courses to keep rows straight. Overhang the eave and rake by about 1/4 to 3/4 inch, or as the maker specifies. Offset the joints from course to course as the instructions show.

Nailing:

  • Use 4 nails per shingle for standard installation, and 6 in high-wind installations or as the maker requires.
  • Place nails in the manufacturer's marked nailing line, usually just below the sealant strip.
  • Drive them straight and flush. Do not overdrive or angle them.

Nails placed too high can miss the layer below, so the shingle pulls off in a storm. Nails placed too low show or leak. High nailing is one of the most common causes of blow-offs.

Sealant strips need warmth from the sun. In cold weather, shingles become brittle and may not seal for weeks. Follow the maker's cold-weather instructions, which may call for hand sealing.

8. Valleys

Valleys carry more water than any other part of a roof. Run ice barrier the full length first.

Valley How it is built
Closed-cut Shingles from one plane extend across the valley, and the other plane's shingles are cut to a line 2 inches from center
Open Metal is left exposed, and shingles are trimmed back on both sides
Woven Shingles from both sides lace over each other. Many makers do not recommend it for architectural shingles

In a closed-cut or open valley, clip the upper corner of each cut shingle so water does not run back under it. Never put nails near the center of a valley.

9. Flashing

Step flashing is individual L-shaped pieces woven into each shingle course where a roof meets a wall. Each piece laps the one below. One leg lies on the shingle, and the other goes up the wall behind the siding. Long single pieces do not work on these walls, because water can run behind them.

Pipe boots. Think about which way water is flowing. Shingles go up to the pipe, and the flange sits on top of them on the low side. Shingles then lap over the flange on the sides and high side. So shingles overlap the flashing on the high side and sides, and the flashing overlaps shingles on the low side. Nail under the shingles, never through the exposed bottom edge.

Chimneys. Use base flashing across the front, step flashing up the sides, and a cricket or saddle behind wide chimneys to split the water. Counterflashing then goes over all of it. It must be embedded in a reglet, which is a groove cut into a mortar joint, and sealed. Surface-caulked flashing is much more likely to fail.

10. Ridge and Hip Caps

Install hip caps from the bottom up, then ridge caps. Start at the end opposite the prevailing wind, so that the laps face away from the wind. Use the maker's cap shingles and a line. Nail each one on both sides, where the next piece covers it. Seal the exposed nails on the last cap.

Ventilation

A roof needs airflow beneath it to carry away heat and moisture. Without it, moisture condenses, and the deck stays hot. Poor attic ventilation is one of the most often cited causes of premature shingle failure, due to excessive heat buildup, and ice dams get worse too.

The usual code ratio is 1 square foot of net free vent area for every 150 square feet of attic floor. It can drop to 1 per 300 when conditions in the code are met, such as about half the vent area being high in the attic.

Balance means roughly equal net free area at the intake (soffits) and exhaust (ridge). Air comes in low and leaves high. Unbalanced ventilation short-circuits this airflow.

Never mix a ridge vent with gable vents on the same attic. Gable vents short-circuit the ridge vent's airflow, leaving stagnant zones. Power vents can cause similar problems.

Worked example. An attic floor is 1,500 square feet.

  • 1,500 / 150 = 10 square feet of net free area.
  • Half at the soffits and half at the ridge = 5 square feet each, or 720 square inches each.

Keep baffles in place so insulation does not block the soffits.

Other Systems

Metal, tile, slate and low-slope membranes each need their own training. Metal must allow for expansion. Tile and slate are very heavy, so the structure must be designed for them. Low-slope roofs use welded or adhered membranes, and they need positive drainage, commonly at least 1/4 inch per foot.

Finding Leaks and Fixing Problems

Problem Likely cause Fix
Leak at a wall Missing or reversed step flashing Rework the flashing
Leak at a pipe Cracked boot Replace the boot
Leak at a valley Short cuts, nails near the center Rework the valley
Blow-offs High nailing, unsealed strips Renail per the instructions
Ice dams Attic heat loss, poor ventilation Air seal, insulate, vent
Curled or blistered shingles Heat, age, poor ventilation Check ventilation, replace

Most leaks start at flashing rather than in the shingle field, so check flashing first.

Roof Hazards to Plan For

Your full fall protection, ladder and heat training comes first. These points are specific to roofing:

  • Stay off wet, frosty or icy shingles. Leave the roof when storms approach.
  • Keep the deck clear of wrappers, cutoffs and loose nails. A loose shingle can slide out from under you.
  • Keep your hose and your lifeline out of the way of each other.
  • Look up before you move metal flashing or ladders near power lines.
  • Barricade the ground below, and sweep with a magnet at the end of each day.

Check Your Understanding

1. A bare deck has no drip edge yet. In what order do the eave drip edge, ice barrier and rake drip edge go on?

Eave drip edge on the deck, ice barrier and underlayment over it, then rake drip edge over the underlayment.

2. A chalk line shows your nails landing above the marked line. Why does that matter?

They can miss the layer below, so the shingle loses its holding power and can blow off.

3. How many squares are on a 2,000-square-foot flat roof area at 8/12?

2,000 x 1.202 = 2,404 square feet, or about 24 squares before waste.

4. A roofer installs a ridge vent, but the old gable vents stay. What is the problem?

The gable vents short-circuit the airflow from the soffits to the ridge. Close them off.

5. At a brick chimney, a helper smears sealant along the top of the counterflashing and calls it done. What should be done?

Set the counterflashing into a reglet cut in the mortar joint, then seal it.

Key Takeaways

  • Water runs from layer to layer, so each lap must face downhill.
  • Drip edge goes under underlayment at eaves and over underlayment at rakes.
  • Standard installation is 4 nails, and 6 in high-wind areas, in the marked nailing line.
  • Step flashing is woven in, course by course. Counterflashing goes in a reglet.
  • Aim for 1 square foot of vent area per 150 square feet of attic floor, balanced.
  • Never mix a ridge vent with gable vents.