Production Supervision

Running Shift Handoffs and Production Boards

20 min read Training Guide

Hand a production area to the next supervisor without losing anything, and run hour-by-hour and SQDC boards that the crew fills in and you act on within the hour.

Table of contents

Two tools carry information across a production floor. The shift handoff carries it from one supervisor to the next, and the boards at each line carry it from the crew to you, hour by hour. Both fail the same way: something gets written down and nobody acts on it. A hold that falls out of a handoff ships to a customer. A board filled in at the end of the shift is a record of what went wrong, written too late to change it.

What You Will Be Able to Do

  • Run a supervisor-to-supervisor handoff that covers safety, quality, delivery, equipment, materials, people and open actions.
  • Write handoff notes the next supervisor can act on without calling you.
  • Set an hourly plan that accounts for breaks and planned changeovers.
  • Read a board for misses and respond within the hour.
  • Turn a week of board reasons into the next problem to fix.

The Supervisor Handoff

Operators pass down notes at their machines. Your handoff is bigger: the whole area, every line, and everything still open.

  • Do it face to face at the production board, during the shift overlap if there is one. If there is no overlap, leave written notes and call the incoming supervisor.
  • Use the same order every time, so nothing gets skipped when the shift was hectic.
  • Walk anything that has to be seen, such as a cage of held parts or a leak with a drip pan under it.
  • Take ownership on arrival. Once the incoming supervisor accepts the handoff, every open item is theirs. Ask questions before you accept, not after.
Topic What to cover
Safety Injuries, near misses, open hazards, any lockout still on
Quality Held parts and where they are, open reports, checks running near a limit
Delivery Each line against plan, hot orders, what runs next
Equipment Machines down, open tickets, temporary fixes, planned maintenance
Materials Shortages and what is staged for the next changeover
People Who is in training and on what, known call-outs, who is on modified work
Open actions What was promised, to whom, and by when

On people, say only what the next supervisor needs to run the shift. "Sam is on modified work, no lifting over 20 pounds" is enough. Medical details and discipline do not belong in a handoff log.

Warning: A lockout still on at shift change stays on. Your plant's energy control program says how lockout protection carries across a shift or personnel change. Never remove another person's lock, and never ask anyone else to.

Weak and Useful Handoff Notes

Topic Weak Useful
Line 2 status Behind 85 short at 2:30. Lost 40 minutes to a feeder jam at noon. At rate since 1:00
Quality Some parts on hold Two bins tagged in the hold cage, lot 4471, bore oversize, parts 1,201 to 1,640. Quality has the report
Equipment Press acting up Press 4 leaking oil at the ram. Ticket 2281 open, drip pan in place, area coned off
Safety Nothing written Near miss at 1:15, forklift and walker at the aisle 3 crossing. Reported, mirror ordered
People Short one Maria signed off on station 2 today. Not yet on station 3

The test for a good handoff: could the incoming supervisor run the first hour from your notes alone? Read your notes back as if you had just walked in and knew nothing.

The Incoming Supervisor's Side

Receiving a handoff is a job too. Ask the questions the notes leave open.

  1. Which parts are affected, and are they all physically tagged and in the hold area?
  2. Has a check passed since the fix, and who confirmed it?
  3. Is anything promised to a customer, another department or maintenance on my shift?
  4. What is the first changeover, and is it staged?

The Hour-by-Hour Board

An hour-by-hour board sits at the line, on a whiteboard or a screen. For each hour it shows the planned output, the actual output, the running totals, and a reason for every hour that missed. Some plants call it a production tracking board. Its value is speed. A loss shows up within the hour, while the people who saw it are still standing there.

Setting the Hourly Plan

The hourly plan comes from the rate the line is planned to run, adjusted for each hour's planned time.

Hourly plan = planned minutes in the hour x 60 ÷ planned cycle in seconds

The planned cycle usually comes from takt time or the scheduled rate. Take planned breaks, lunch and planned changeovers out of the minutes, so the crew is not marked as missing for a planned event.

Worked example. A line is planned at a 45-second cycle, which is 3,600 ÷ 45 = 80 parts in a full hour. The shift has a 10-minute break in hour 3, a 30-minute lunch in hour 5, and a 10-minute break plus a 20-minute planned changeover in hour 7.

Hour Planned minutes Plan Running plan
1 60 80 80
2 60 80 160
3 50 66 226
4 60 80 306
5 30 40 346
6 60 80 426
7 30 40 466
8 60 80 546

Hour 3 works out to 50 x 60 ÷ 45 = 66.7. Round down so the board never asks for part of a part. The shift plan is 546.

Planning around the changeover keeps the board fair to the crew, but the changeover minutes still count as lost availability in OEE. Record the planned and actual changeover minutes on the board so both numbers stay honest.

Filling In the Board

  1. The operator or lead at the line writes the actual count at the end of each hour. Not you, and not at the end of the shift.
  2. Every hour under plan gets a reason in plain words with minutes: "Feeder jam, 12 min."
  3. Mark each hour green when it meets plan and red when it falls short, or use your plant's marks.
  4. Whoever fills it in initials it.

Here is the same line after five hours.

Hour Plan / actual Running plan / actual Reason for a miss
1 80 / 64 80 / 64 Late material, 12 min
2 80 / 80 160 / 144
3 66 / 58 226 / 202 Feeder jam, 6 min
4 80 / 81 306 / 283
5 40 / 26 346 / 309 Waiting on inspector, 10 min

After five hours the line is 37 short. Two of the three misses came from waiting on something outside the line, material and an inspector. That tells you more than a total at the end of the shift would.

Responding to a Miss

A red hour with no response teaches the crew that the board does not matter. Make the board part of your hourly walk.

  1. Read every board in your area each hour, or as often as your walk allows.
  2. For each red hour, ask the person at the line what happened. Listen before you suggest anything.
  3. Decide: is it fixed, does it need someone else, or does it need to go up the escalation ladder?
  4. Write the action on the board's action list with a name and a time.
  5. If a red hour has no reason, ask for it. Do not fill it in yourself from your desk.

Never use the board to blame people. A board used for blame gets numbers that look good, and the real problems go quiet.

Turning Board Reasons Into Fixes

A week of reasons shows you where the line really loses time. Tally them by minutes lost, not only by how many times they happened.

Reason Times Minutes lost
Feeder jams 14 126
Waiting for material 6 95
Changeover over plan 4 60
Waiting on inspection 5 40
Other 3 15

The week lost 336 minutes. Feeder jams and waiting for material together are 221 minutes, about two-thirds of the total. Jams happen most often, but each material wait costs about 16 minutes against 9 for a jam, so both are worth attacking.

  1. Pick the top one or two by minutes.
  2. Give each an owner by name and a date.
  3. Find the cause with the people who see it happen, instead of guessing from the office.
  4. Watch the same tally next week to see whether the fix held.

The SQDC Board

An SQDC board shows the team's daily results on four measures: safety, quality, delivery and cost. Some plants add P for people. Each measure usually gets a monthly calendar shaped like its letter, or a cross for safety, with each day colored green or red. Next to the calendars sit a trend chart for each measure and the action list.

Measure A day goes red when (example)
Safety Any injury, or a near miss with no action yet
Quality Any part held, or scrap over the area's target
Delivery The shift missed its plan
Cost Overtime or scrap over budget

Your plant sets what turns a day red. Keep the rules posted on the board so nobody argues about the color.

The Action List

What Who When Status
Fix feeder track on line 2 R. Diaz Thu Parts ordered
Add mirror at aisle 3 crossing J. Park Fri Done, verified
  • One owner, by name. "Maintenance" is not a name.
  • A date, reviewed at every meeting.
  • Close an item only when the fix is checked and working, not when someone says it is done.

Daily Meetings at the Boards

Many plants run short meetings at the boards in tiers.

  • Tier 1: the crew and its lead or supervisor at the line board, at the start of the shift.
  • Tier 2: supervisors with their area manager, for problems that need help from another area.
  • Tier 3: the plant manager with department heads, for problems the area cannot solve.

A problem moves up a tier when the lower one cannot solve it, and the answer comes back down to the person who raised it. That return trip matters. If people raise problems and never hear back, they stop raising them.

Common Mistakes

Mistake What it costs
Filling in the board at the end of the shift Numbers nobody trusts, and no chance to react
Red hours with no reason Nothing to fix
Using the board to blame operators Numbers that look good while problems hide
A plan that ignores breaks and changeovers Planned events look like failures, and the crew stops caring
A handoff by text message only Questions go unasked and holds get missed
Actions owned by a department instead of a person Nobody does them

Check Your Understanding

1. A line is planned at a 40-second cycle. Hour 4 has a 10-minute break. What is its plan?

There are 50 planned minutes. 50 x 60 ÷ 40 = 75 parts.

2. You arrive and the handoff note says, "Line 3 had a quality issue, fixed." What do you ask before you accept it?

Which parts were affected, how many, and whether they are tagged in the hold area. Whether there is a report, who owns the decision, what was fixed, and whether a check has passed since. Then walk to the hold area and look.

3. A board shows three red hours in a row, each with the reason "slow." What is wrong, and what do you do?

"Slow" is not a reason anyone can fix, and three misses in a row means nobody responded after the first. Go to the line, find out what is really slowing it, act or escalate, and coach the crew to write the cause and the minutes.

4. A week's tally shows 20 short jams totaling 60 minutes and 3 material waits totaling 90 minutes. Which do you work on first?

The material waits, because they cost more time. Counting events alone would have pointed you at the jams.

5. A mechanic's lock is still on press 2 at shift change, and the mechanic has gone home. Your manager tells you to cut it off so the press can run. What do you do?

Do not cut it. Only the lock removal procedure in your plant's energy control program can authorize removing a lock when its owner is gone, and it has steps that must be followed first. Escalate to whoever the program names.

Key Takeaways

  • Hand off face to face, at the board, in the same order every time, and walk anything that needs to be seen.
  • Write handoff notes with facts, numbers and locations that the next supervisor can act on.
  • Set the hourly plan from planned minutes and the planned cycle, and take out breaks and planned changeovers.
  • The crew fills in the board each hour, every miss gets a reason, and you respond within the hour.
  • Tally a week of reasons by minutes lost, and give the top ones an owner and a date.
  • An action closes only when the fix is checked, and answers go back to the person who raised the problem.