Find the property line, call 811, lay out a straight fence line, dig holes to the right depth, and set posts plumb in concrete or gravel so they stay put.

Table of contents

A fence is only as straight and solid as its posts. Rails, pickets and chain-link fabric hang on the posts, and wind pushes on the whole fence as if it were a sail. A post set too shallow leans in a year. One set above the frost line rises out of the ground in winter. One set on the wrong side of the property line can cost the owner the whole fence. Setting posts right is most of the work of building a fence.

Post depth, hole size and setting methods vary with soil, climate, fence height and the fence maker. The numbers below are common practice. Your town's rules, the job specification and the fence maker's instructions win.

What You Will Be Able to Do

  • Confirm where the fence can go before anyone digs.
  • Get utilities marked and dig safely around the marks.
  • Lay out a straight line with even post spacing and square corners.
  • Size holes and pick a depth for the soil and climate.
  • Set posts plumb in concrete or compacted gravel.

Before Anyone Digs

Property Line and Permits

  1. Find the line. Use the survey or plat and look for the iron pins or monuments at the corners. Do not trust an old fence or a neighbor's word. If there is any doubt, the owner needs a licensed land surveyor.
  2. Check the rules. Many towns require a fence permit and set height limits, setbacks from the line or the street, and which side of the fence faces out. Homeowner associations often add their own rules.
  3. Pools are different. A fence around a pool is a safety barrier with its own code, including height, gaps and self-closing, self-latching gates. Build it to the local pool barrier rule.
  4. Stay inside. Many installers set posts a few inches inside the property line, so the concrete does not cross onto the neighbor's land.

Call 811

Every state has a one-call center that has utility owners mark their buried lines for free. Fence holes are digging, and state law requires the call.

  1. Call 811 or file online a few business days before digging. Your state's law sets the exact notice and how long the ticket lasts.
  2. Wait until every utility on the ticket has marked or cleared before you dig.
  3. Inside the tolerance zone around each mark, usually 18 to 24 inches on each side depending on your state, dig only by hand, gently, until you can see the line.
  4. 811 does not mark private lines. Ask the owner about sprinkler pipes, landscape lighting, a gas line to a grill or pool heater, a buried pet fence wire, or a feed to a shed. A private locator can find them.

If you hit or nick a line, stop, keep people away, and call the utility. For gas, leave the area and call 911.

Laying Out the Line

  1. Stake the ends and corners. Set a stake at each end post, corner and gate post.
  2. Square the corners. Use a 3-4-5 triangle, or 6-8-10 for more accuracy.
  3. Run a string between the stakes, tight and a little above the ground. Many crews offset the string an inch or two from where the post faces will land, so posts do not push it out of line.
  4. Mark the posts. Measure on center from the end post along the string. Common spacing is 6 to 8 feet for wood fences. Panels and rails come in set lengths, so set your spacing to fit them.
  5. Lay out gates. Gate openings come from the gate width plus the hinge and latch clearance the hardware calls for. Mark gate posts carefully, since a gate opening cannot be adjusted later.

Divide runs evenly. A 46-foot run does not divide into 8-foot sections. 46 / 8 = 5.75, so use 6 sections of 46 / 6 = 7 feet 8 inches each, instead of five full sections and one short one.

Choosing Posts

Post Use
4x4 treated, ground-contact rated Line posts on most wood fences
4x6 or 6x6 treated Gate posts, tall fences, high wind
Galvanized steel post Chain-link, or steel posts behind wood fences
Cedar or redwood Only the heartwood resists rot in the ground

Treated lumber for posts must be rated for ground contact on its tag. An above-ground rating is not enough. Cut the top of a treated post, not the bottom, because the factory-treated end goes in the ground. Brush preservative on any cut end.

Sizing the Hole

Depth

  • A common rule is to bury one-third to one-half of the post's above-ground height, so 2 to 3 feet for a 6-foot fence.
  • Where the ground freezes, go below the local frost line. Ask the building department for it.
  • Gate posts, corner posts and end posts carry more force. Go deeper and wider on those.
  • Taller and solid fences catch more wind than short or open ones, so they need deeper posts.

Width

A common rule is a hole about three times the width of the post. That is roughly 10 to 12 inches for a 4x4. The concrete or gravel around the post is what keeps it from tipping, so a hole that is too narrow leaves a weak collar.

Shape and Frost

Keep the sides straight, or slightly wider at the bottom. A hole that flares out at the top, or concrete that mushrooms over the ground, gives frozen soil something to grip and lift. Frost lifting a post this way is called frost heave.

Digging Tools

Tool Best for
Clamshell post-hole digger A few holes, tight spots, near utility marks
Digging bar Breaking rock and hard soil, prying out roots
Gas auger, one or two person Many holes in soil without much rock
Tow-behind or machine auger Long fences and hard ground

Warning: A handheld auger can twist violently when it binds on a root or rock and can throw an operator. Use one with a torque control or a frame that braces against your body, keep a firm stance, keep loose clothing away, and shut it off before you clear the bit.

Pile the spoil on a tarp, away from the hole edges, so it does not fall back in or bury the string.

Setting Methods

Method Strengths Weaknesses
Concrete Strongest hold, the usual choice for gate posts Hard to remove, traps water if not crowned
Compacted gravel Drains well, easy to replace a post Not as rigid in soft soil
Fast-setting concrete Quick, no mixing tub Follow the bag exactly
Expanding foam Light and fast Check the maker's limits, often not for gates

Setting in Concrete

  1. Put about 4 to 6 inches of gravel in the bottom and tamp it, so water drains away from the post end.
  2. Set the post on the gravel and turn it so its faces line up with the string.
  3. Plumb it on two adjacent faces with a post level, and brace it both ways with stakes and scrap boards screwed to the post.
  4. Fill with concrete, mixed or poured as the bag says. Some fast-setting mixes go in dry with water added on top, and others are mixed first.
  5. Rod the concrete with a stick to remove air pockets. Check plumb again.
  6. Finish the top above grade and slope it away from the post, so water runs off instead of pooling against the wood.
  7. Leave the braces on, and do not hang rails or a gate until the concrete has cured as long as the bag says.

Setting in Gravel

  1. Put a few inches of gravel in the bottom and tamp it.
  2. Set and plumb the post.
  3. Add crushed stone with sharp edges in lifts of about 4 to 6 inches, and tamp each lift hard with a bar or tamper. Round pea gravel rolls and does not lock.
  4. Recheck plumb after every lift.

Worked Example

A 6-foot privacy fence is going up where the frost line is 36 inches. Holes are 12 inches across, with 6 inches of gravel under each post.

  1. Post length: 36 inches below grade + 72 inches above = 108 inches. Buy 10-foot posts and trim the tops later.
  2. Hole depth: 36 + 6 = 42 inches.
  3. Concrete around one post, 36 inches deep: the hole holds 3.1416 x 6 x 6 x 36 = 4,072 cubic inches. The post takes 3.5 x 3.5 x 36 = 441. That leaves 3,631 cubic inches, or 3,631 / 1,728 = about 2.1 cubic feet.
  4. An 80-pound bag of concrete yields about 0.6 cubic foot. 2.1 / 0.6 = 3.5, so plan on 4 bags per post.
  5. For 14 posts, buy about 56 bags, plus a few extra.

Lining Them Up

  1. Set the end, corner and gate posts first, and let them cure.
  2. Run two strings between them, one near the top and one near the bottom, on the face the rails will attach to.
  3. Set each line post to touch both strings without pushing them. Check the on-center spacing at the top as well as the bottom.
  4. On a slope, decide before you start whether the fence will step, with each section level and the tops stepping down, or rack, with the rails following the ground. Panels and posts are set differently for each.
  5. Cut the tops to height after setting, using a string, a level line or a laser, so the line of tops is even. Cut tops at an angle, or add caps, so they shed water.

Common Mistakes

Mistake What it costs
Trusting an old fence as the property line A fence on the neighbor's land
Digging before 811 marks are complete A struck gas, power or fiber line
Holes too shallow or above the frost line Leaning posts and heaved gates
Concrete that mushrooms at the top Frost lifts the post, and water pools on the concrete
Above-ground lumber in the ground Rot at the ground line in a few years
Measuring each post from the last one Small errors add up until panels do not fit

Check Your Understanding

1. A homeowner says the property line is the old chain-link fence. What do you do?

Find the survey and the corner pins. If the line is still unclear, the owner needs a licensed surveyor before you dig.

2. 811 marks are down for power and gas, but the cable company has not responded and the wait time has passed. Can you dig?

Not until every utility on the ticket has marked or cleared, as your state's process requires. Call the one-call center to follow up.

3. A 6-foot wood fence's gate post is set in a 10-inch hole, 18 inches deep, with the concrete flared over the lawn. What will happen?

It is likely to lean under the gate's weight and may heave in winter. Gate posts need deeper, wider holes with straight sides and a crowned top that does not spread over the ground.

4. You need 9 posts set in 12-inch holes with about 2.1 cubic feet of concrete each. How many 80-pound bags do you buy?

9 x 2.1 = 18.9 cubic feet. 18.9 / 0.6 = 31.5, so at least 32 bags, plus a few extra.

Key Takeaways

  • Confirm the property line, the permit and any pool rules before digging.
  • Call 811, wait for every utility, hand dig inside the tolerance zone, and ask about private lines.
  • Set end, corner and gate posts first, and string the line from them.
  • Go deep enough for the fence height and below the frost line where the ground freezes.
  • Use ground-contact posts, plumb them on two faces, and crown the concrete so water runs off.