Skills / Construction Crew Leadership / Construction Foreman Development / Doing a Material Takeoff from Drawings
Construction Crew Leadership

Doing a Material Takeoff from Drawings

15 min read Training Guide

Count and measure the material for your crew's scope from the plans, specs and schedules, keep a takeoff sheet someone else can check, add waste the right way, and turn quantities into an order.

Table of contents

A material takeoff is a list of every item and quantity needed for a scope of work, measured from the drawings and specifications. An estimator does takeoffs to price a bid. A foreman does them to order material, check what the estimate assumed, plan deliveries and catch a shortage before it stops the crew. A good takeoff is organized, so anyone can see where each number came from and check it. A bad one is a pile of numbers nobody can trust. This guide covers the method, with worked examples for concrete, framing and drywall.

What You Will Be Able to Do

  • Define your scope before you count anything.
  • Pick the right unit for each item, the way suppliers sell it.
  • Organize a takeoff by system and area, with sheet references.
  • Measure concrete, framing and drywall quantities from a plan.
  • Add waste and round to order quantities.
  • Check a takeoff with a second method.

Before You Count

  1. Get the current set. Check the revision column and any clouds. A takeoff from a superseded sheet is wrong from the first number.
  2. Read your scope. Your contract or the estimate says what your crew is responsible for. Notes like "by others," "N.I.C." (not in contract) or "by owner" mean someone else supplies or installs that item.
  3. Read the specifications for your work. They name the material, grade, thickness, fasteners and accessories. The drawings show how much and where. The specs show what.
  4. Read the general notes on your discipline's sheets. A note like "all exterior walls 2x6 at 16 inches on center unless noted" changes every count.
  5. Check the schedules. Door, window, finish, fixture and equipment schedules list items you count directly.

Use written dimensions. Measure from the drawing with a scale only when a dimension is missing, and confirm the print scale first, since half-size prints are common.

Units Suppliers Use

Count each item in the unit you will order it in, or convert at the end. Mixing units is one of the most common takeoff errors.

Unit Abbreviation Used for
Each EA Doors, fixtures, anchors, studs by the piece
Linear feet LF Plates, trim, pipe, wire, sealant joints
Square feet SF Sheathing, drywall, insulation, flooring
Square yards SY Carpet, some paving. 1 SY = 9 SF
Roofing square SQ Shingles, underlayment. 1 SQ = 100 SF
Cubic yards CY Concrete, fill, gravel. 1 CY = 27 cubic feet
Board feet BF Lumber by volume. Thickness in inches x width in inches x length in feet, divided by 12
Tons TN Gravel, asphalt, rebar in large amounts

Lumber is named by its nominal size, such as 2x4, which is about 1-1/2 x 3-1/2 inches actual. Use the nominal size for board feet and the actual size for fitting.

Organize the Takeoff Sheet

Use a spreadsheet or your company's software, with one line for each item in each area.

Sheet Area Item Quantity
A2.1 Level 1, east 2x6 studs, 9 ft 142 EA
A2.1 Level 1, east 2x6 plate 486 LF
A2.2 Level 2, east 5/8 Type X drywall, 4x12 96 EA

Add columns for the unit, the waste factor and the order quantity. The sheet and area columns let someone check your work and let you order by area as the job moves.

Mark the drawings as you go. Use a highlighter or the color tool in your software. Color each wall, room or item as you count it. Anything not colored at the end was missed, and anything colored twice was double counted.

Work by system, then by area. Count all the walls on level 1, then all the walls on level 2. Do not jump between drywall and framing on the same sheet.

Worked Example: A Garage Slab

The plan shows a slab 24 feet by 30 feet, 4 inches thick, with a thickened edge 12 inches wide and 12 inches deep below the slab around the whole perimeter. Your company adds 5 percent for waste on slabs. That figure is only for this example. Use your company's number.

  1. Slab volume. 4 inches = 4 / 12 = 0.333 feet. 24 x 30 x 0.333 = 240 cubic feet.
  2. Thickened edge. Perimeter = 2 x (24 + 30) = 108 feet. The extra section is 1 foot wide x 1 foot deep, so 108 x 1 x 1 = 108 cubic feet. The corners overlap slightly, which this simple method ignores, and it errs a little on the high side.
  3. Total. 240 + 108 = 348 cubic feet.
  4. Convert to cubic yards. 348 / 27 = 12.89 CY.
  5. Add waste. 12.89 x 1.05 = 13.53 CY.
  6. Round to the order. Order 14 CY, or what your supplier's increments allow.

Ask your supplier about truck capacity and any fee for a short last load. Check the subgrade before the pour. A base that is low by 1 inch across this slab adds 24 x 30 x (1/12) = 60 cubic feet, or more than 2 CY.

Worked Example: An Exterior Wall

A wall is 40 feet long and 8 feet tall, framed with 2x6 studs at 16 inches on center, with a single bottom plate and a double top plate. It has two windows.

  1. Common studs. 40 feet = 480 inches. 480 / 16 = 30 spaces, plus 1 stud to close the end = 31 studs.
  2. Openings. Your company's rule for this kind of wall is to add 4 studs for each window, for king and jack studs, and keep the studs the opening removes for cripples and blocking. That gives 2 x 4 = 8 more.
  3. Corners and intersections. Add what your corner and partition details call for. Say 3 at each end, so 6 more.
  4. Total studs. 31 + 8 + 6 = 45 studs.
  5. Plates. 3 plates x 40 feet = 120 LF. In 16-foot pieces, 120 / 16 = 7.5, so 8 pieces. Plan the splices so top plate joints stay offset as the framing details require.
  6. Headers. Take the size and length from the plans or header schedule for each opening. Do not guess at a header size.
  7. Sheathing. 40 x 8 = 320 SF. 320 / 32 = 10 sheets of 4x8. Many crews sheath over window openings and cut them out, so do not deduct small openings unless your company's rule says to.

Engineered lumber, hold-downs and connectors come from the structural sheets and their schedules. Count each one exactly as specified, with its fasteners.

Worked Example: Drywall for a Room

A room is 14 by 16 feet with a 9-foot ceiling. It has one 3-by-7-foot door and one 4-by-5-foot window. The drywall comes in 4x12 sheets, which cover 48 SF.

  1. Walls. Perimeter = 14 + 16 + 14 + 16 = 60 feet. 60 x 9 = 540 SF.
  2. Openings. Door 3 x 7 = 21 SF. Window 4 x 5 = 20 SF. Many estimators deduct only large openings, such as overhead doors, because the cutouts are waste anyway. Follow your company's rule. This example deducts nothing.
  3. Ceiling. 14 x 16 = 224 SF.
  4. Total. 540 + 224 = 764 SF.
  5. Sheets. 764 / 48 = 15.9, so 16 sheets before waste.

Hanging layout matters more than area here. A 9-foot wall takes 4-foot sheets laid horizontally with a strip at the top or bottom, and some crews order 54-inch-wide sheets to fill a 9-foot wall in two rows. Count by how your crew will actually hang it.

Waste and Rounding

Waste covers cut-offs, damage, mistakes and pieces too short to use. It differs by material, layout, crew and job.

  • Use your company's history first. Compare what was ordered with what was installed on past jobs.
  • Add waste to the quantity, then round up to the unit you can buy. Rounding first and then adding waste overstates the order.
  • Add more for complex layouts, such as diagonal tile, many corners or short walls.
  • Record what you actually used. Your next takeoff gets better.

Do not forget the accessories: fasteners, adhesive, tape, corner bead, sealant, shims and blocking. Specs often list them. A crew stopped for lack of screws loses the same day as one stopped for lack of drywall.

Checking the Takeoff

  1. Use a second method. For drywall, compare your sheet count with total area divided by sheet size. For framing, compare studs per foot of wall with a past job.
  2. Compare with the estimate. If your takeoff is 20 percent over or under the estimator's, find out why before you order. One of you missed something.
  3. Look for what is not colored on the marked-up drawings.
  4. Check revisions since you started. A bulletin or answer to a question can add or remove work.
  5. Have someone else spot-check a few lines.

From Takeoff to Order

  • Order by area and by schedule, so material arrives when the crew needs it, not all at once.
  • Find long-lead items early, such as special doors, windows, engineered beams or custom steel. Some need approved submittals before they can be ordered, and lead times can run weeks or months.
  • Confirm the material matches the spec, including grade, fire rating and thickness.
  • Keep the takeoff with the order, so you can check deliveries against it.

Common Mistakes

Mistake What it costs Better habit
Counting from an old revision Wrong material, rework Check the revision first
Scaling a half-size print Every length is wrong Use written dimensions, and confirm the print scale
Double counting Overbuying Color items as you count
Mixing SF and SY, or CF and CY Orders off by 9 or 27 times Write the unit on every line
Rounding before adding waste Too much material Add waste, then round up
Forgetting accessories The crew stops for screws or tape List fasteners and accessories from the specs
Missing "by others" notes Buying what someone else supplies Read the scope and notes first

Check Your Understanding

1. A slab is 20 by 40 feet and 6 inches thick. How many cubic yards is it, before waste?

20 x 40 x 0.5 = 400 cubic feet. 400 / 27 = 14.81 CY.

2. A 2x4 interior wall is 24 feet long at 16 inches on center, with no openings. How many common studs?

24 x 12 = 288 inches. 288 / 16 = 18 spaces, plus 1 = 19 studs, before corners and intersections.

3. You measure 1,350 SF of carpet. Your supplier sells by the square yard. What do you order before waste?

1,350 / 9 = 150 SY.

4. Your drywall takeoff for a floor is 30 percent lower than the estimator's. What do you do before ordering?

Find out why. Compare the areas, the sheet sizes, the ceiling heights and the revision each of you used. One of you missed something, and it is cheaper to find it now.

5. You calculate 9.6 sheets of sheathing and your company adds 10 percent waste. What do you order?

9.6 x 1.10 = 10.56, rounded up to 11 sheets.

Key Takeaways

  • Define your scope and read the specs and notes before you count.
  • Write a unit on every line, and know the conversions: 9 SF in a SY, 27 cubic feet in a CY, 100 SF in a square.
  • Organize by system and area, with sheet references, and color the drawings as you count.
  • Add waste from your company's history, then round up to what you can buy.
  • Check with a second method, and find out why your number differs from the estimate.
  • Order by area and schedule, and catch long-lead items early.