Coordinating Subcontractors and Deliveries

20 min read Training Guide

Get each subcontractor ready before they mobilize, run a coordination meeting that sorts out who works where, hand off areas with a record, and plan, receive and store deliveries safely.

Table of contents

A building goes up through many companies working in the same space. Each subcontractor has its own foreman, its own crew and its own schedule pressure. Deliveries arrive by the truckload and need a place to go. When nobody coordinates, two crews show up to the same room, a truck blocks the crane, and a pallet of drywall sits in the rain. When someone coordinates well, the job feels calm. On a general contractor's job, coordination falls to the superintendent and the foremen who help run the site. This guide covers working with subcontractors before, during and after their work, and handling deliveries from the call to the storage spot.

What You Will Be Able to Do

  • Confirm a subcontractor is ready to start before they mobilize.
  • Run a short coordination meeting that sorts out areas and handoffs.
  • Hand an area from one trade to the next with a record of its condition.
  • Deal with a subcontractor's safety problem or damage through the right channel.
  • Plan a delivery's time, route, unloading and storage.
  • Receive material and record damage or shortages correctly.

How the Relationship Works

A subcontractor works for the general contractor under a subcontract, which sets its scope, price, schedule duties and rules. The subcontract governs, so ask your project manager what it says about schedule, cleanup, damage and safety.

  • Direct the company, not its workers. Give instructions to the subcontractor's foreman or superintendent. If you tell their workers directly how to do their work, you blur who is responsible, and you may be giving directions their own employer would not.
  • Your site rules apply to everyone. Orientation, PPE, hours, parking, housekeeping and stop-work rules cover every company on the site.
  • One hazard can be on many employers. Under OSHA's multi-employer policy, more than one employer can be cited for the same hazard, including the general contractor with control of the site. If you see a hazard from a subcontractor's work, stop the exposure and tell their foreman right away.

Before a Subcontractor Mobilizes

A subcontractor who shows up to an area that is not ready loses money and may leave for another job. Check these at least a week before their start.

Item What to confirm
Scope What they include and exclude, and who does the gray areas, such as blocking, sleeves or cleanup
Submittals Their shop drawings and product data are approved, so material can be ordered
Material Ordered, with delivery dates that fit the start
Area Prior work done, inspected where needed, and clear
Access Hoisting, stairs, power, lighting, water and a place to stage
Safety Site orientation booked, their task hazard analysis, their competent persons and required certifications
Schedule Start date, crew size and duration they commit to

Your project manager usually handles insurance and contract paperwork. Ask whether the subcontractor is cleared to start before they arrive.

The Kickoff Meeting

Hold a short meeting with the subcontractor's foreman before their first day on site. Walk the areas they will work in. Cover the schedule and look-ahead, the sequence, site logistics, the hazards near their work, how they will receive and store material, how to raise questions, and who on your side they should call. Write down what was agreed, and send it to them.

The Coordination Meeting

Most sites hold a regular meeting, often weekly, with every trade foreman, plus a short daily check on busy jobs.

  1. Look ahead. Go through the next two to three weeks of the schedule, area by area.
  2. Who is where. Each trade says where it will work each day. Find the overlaps.
  3. Handoffs. Which areas are finishing, and which trade takes them next.
  4. Constraints. Open questions, late material, inspections and access problems, each with a name and a date.
  5. Safety. Crane picks, hot work, overhead work, shutdowns and changes to walkways.
  6. Action list. Who does what by when. Send it out the same day.

Sorting Out Stacked Trades

When two trades need the same area, decide based on the schedule, not on who complains loudest.

  • Split the area by room, grid line or floor, so each crew has its own space.
  • Sequence it, such as overhead work first, then the trade below, so nobody works under someone else's load.
  • Split the day, with one trade in the morning and one in the afternoon, when the space is small.
  • Check the critical path. A trade on the critical path usually gets priority.

Never let crews work stacked, one over the other, unless the overhead work is protected, such as with netting, debris protection or a barricaded zone below.

Handing Off an Area

When one trade finishes an area and another takes it over, walk it together.

  1. Confirm the first trade's work is complete, inspected if needed, and cleaned up.
  2. Note any damage, missing items or open punch list, with photos and dates.
  3. Have both foremen agree, in writing or by email, that the area is ready.
  4. Protect finished work that the next trade could damage, such as floors, doors or casework.

This record settles most damage disputes before they start. Without it, every scratch becomes an argument.

Damage and Backcharges

When one trade damages another's work, document it right away: photos, location, date and what you saw. Tell the responsible subcontractor's foreman and your project manager the same day. A backcharge is a cost the general contractor charges to a subcontractor, for example to repair damage that subcontractor caused. The subcontract sets the notice and the process, so do not hold back money or threaten it in the field. Give your project manager the facts.

Planning Deliveries

Every delivery uses time, space and often equipment. Plan it like any other task.

Question Why it matters
When does it arrive? Avoid two big trucks at once, and avoid a concrete pour or crane pick at the same time
What size truck? It needs room to enter, turn and leave, and ground firm enough to hold it
How is it unloaded? Forklift, boom truck, crane or by hand, with a qualified operator and rigging
Where does it go? A planned laydown spot near the work, not wherever there is room
Is the route clear? Gates, overhead lines, trenches, soft ground and walkways
Who receives it? Someone who knows what was ordered and can check it

Ask suppliers for a delivery window, and give the driver the site address, gate, contact name and phone number. If a load needs a crane or boom truck, plan the lift before the truck arrives, including the power line clearance and who signals.

Just in Time or Early

Approach Good for The risk
Deliver as needed Tight sites, material that is easy to damage, weather-sensitive material A late truck stops the crew
Deliver early Long-lead items, large orders, remote sites Storage space, damage, theft and handling twice

Backing Vehicles and Spotters

Trucks backing on a site are a major struck-by hazard. Under 29 CFR 1926.601(b)(4), a vehicle with an obstructed view to the rear may not be used unless it has a reverse signal alarm audible above the surrounding noise, or is backed up only when an observer signals that it is safe. Even with an alarm, use a spotter where people are working nearby.

  • Keep the spotter in the driver's view at all times. If the driver loses sight of the spotter, the driver stops.
  • Agree on hand signals before the truck moves.
  • Keep everyone else out of the backing path.
  • Spotters do not stand between the truck and a fixed object.

Receiving Material

  1. Check the delivery ticket against your order or takeoff: item, size, grade, quantity.
  2. Count it before the driver leaves.
  3. Inspect it for damage, such as broken pallets, wet drywall, dented doors or bent studs.
  4. Write any problem on the ticket before you sign it, such as "2 doors with dented frames" or "short 1 bundle." Take photos. Suppliers and carriers may refuse a claim on a ticket that was signed clean.
  5. Refuse material that is wrong or badly damaged, if your company allows it, and tell your project manager right away.
  6. Record the delivery in your daily report, and send the ticket to the office.

Storing Material Safely

OSHA's rules on material storage in construction are at 29 CFR 1926.250. Some key points:

  • Material stored in tiers must be stacked, racked, blocked, interlocked or otherwise secured to keep it from sliding, falling or collapsing.
  • The weight of stored material on floors may not exceed the safe load limit. Floor load limits must be posted in storage areas, except on a slab on grade, and in single-family or wood-frame multi-family residential buildings.
  • Inside a building under construction, material may not be stored within 6 feet of a hoistway or an inside floor opening, or within 10 feet of an exterior wall that does not extend above the top of the stored material.
  • Aisles and passageways must be kept clear for the safe movement of equipment and people.

Warning: Do not land a heavy load on an elevated deck, a new slab or framing without knowing it can carry it. Pallets of drywall, block or roofing are heavy, and a concentrated load can overload a floor that was designed for spread-out weight. Ask the superintendent and, where needed, the engineer where loads may go.

Protect material from weather and damage. Keep drywall and insulation dry and off the ground, keep lumber flat on blocking, and store items that can be stolen in a locked area. Material ruined in storage has to be bought again.

Worked Example: A Busy Morning

On Tuesday you have a concrete pour for a sidewalk starting at 7 a.m., a truss delivery that needs a crane, and a drywall delivery for the inside.

  1. Pour first. Concrete trucks need the main access from 7 to about 10 a.m. Nothing else uses that route then.
  2. Trusses at 10:30 a.m. The crane sets up after the pour trucks leave, on ground the superintendent has checked. Its swing area is barricaded, and the truss delivery truck parks where the plan shows.
  3. Drywall at 1 p.m. Delivered through the back gate to the boom truck's landing spot on the level 1 slab on grade, away from the crane.
  4. Tell everyone. The schedule goes to every foreman and supplier on Monday, with the gate, times and contact name for each truck.

If the drywall supplier can only come at 9 a.m., move it to another day. Do not put three operations in one access lane to save a phone call.

Common Mistakes

Mistake What it costs Better habit
Sub shows up to an area that is not ready Wasted trip, lost goodwill Confirm readiness a week ahead
Directing a sub's workers yourself Confused responsibility Go through their foreman
No handoff walk Damage disputes Walk, photograph and agree in writing
Two big deliveries at once Blocked access, idle crane Give each truck a window
Signing a clean ticket for damaged goods Claim refused Note damage before you sign
Pallets landed on any open floor Overloaded deck Ask where loads may go
Material stored near an opening Falling objects, falls Keep 6 feet from openings and hoistways

Check Your Understanding

1. The electrician's crew is pulling wire in a corridor where your drywall crew is scheduled to hang ceiling today. What do you do?

Talk to the electrical foreman, not the crew. Split the area or the day, or move your crew to a ready area, based on what the schedule needs. Bring it to the next coordination meeting.

2. A delivery of 50 doors arrives and 3 have dented skins. The driver wants a signature. What do you do?

Count and inspect, write "3 doors with dented skins" and the door numbers on the ticket before you sign, take photos, and tell your project manager.

3. The roofer wants to land four pallets of shingles on the second-floor deck right next to the stair opening. What rules apply?

Material may not be stored within 6 feet of an inside floor opening, and the load may not exceed what the floor can safely carry. Ask the superintendent where the pallets may go before they are landed.

4. A dump truck with no working backup alarm needs to back into the site. Can it?

Only if it is backed up when an observer signals that it is safe. Use a spotter in the driver's view, and keep others out of the path.

5. The painter says your carpenters scratched finished doors in a hallway that was handed off yesterday. What helps settle it?

The handoff record: photos and the agreed condition of the hallway at handoff. Give your project manager the facts, and let the subcontract process handle any backcharge.

Key Takeaways

  • The subcontract governs scope, schedule, damage and backcharges.
  • Direct a subcontractor through its foreman, and apply site safety rules to everyone.
  • Confirm scope, submittals, material, area, access and safety before a sub mobilizes.
  • Hand off areas with a walk, photos and written agreement.
  • Give each delivery a time, route, unloading plan and storage spot.
  • Note damage on the ticket before you sign, and store material away from openings and within floor limits.