Skip to content
Construction Crew Leadership

Managing Change Orders

15 min read Training Guide

Spot work that is outside your contract, give notice before you do it, track extra work on signed time and material tickets, and give your project manager the facts to price the change and its time.

Table of contents

A change order is a written agreement that changes the contract after it is signed. It can change the work, the price, the time, or all three. Changes are normal on almost every job. The money is lost when a crew does extra work without anyone noticing it was extra, or without the records to prove what it cost. The foreman is usually the first person to see a change, so the foreman decides whether it gets paid for. This guide covers how to recognize a change, what to do before you build it, how to track it, and how it gets priced.

Note: The contract controls everything in this guide. Who may approve a change, how fast you must give notice, what markup is allowed and how disputes are handled are all set by your contract and subcontract, and they vary from job to job. Ask your project manager what yours says. This is not legal advice.

What You Will Be Able to Do

  • Tell changed work from base contract work.
  • Name the common sources of changes.
  • Give written notice before doing changed work.
  • Fill out a time and material ticket that will hold up.
  • Gather the labor, material, equipment and time a change needs to be priced.
  • Handle a request from the owner in the field.

The Paperwork Behind a Change

Many jobs use standard contract forms. You will hear these names, and your project manager handles their terms.

Form family General conditions Change order Change before price is agreed
AIA A201, General Conditions of the Contract for Construction G701, Change Order G714, Construction Change Directive
ConsensusDocs 200, Agreement and General Conditions Between Owner and Constructor 202, Change Order 203, Interim Directed Change

Subcontracts have their own versions, such as AIA A401 and ConsensusDocs 750, and many companies write their own contracts. The ideas below are common to most of them, but the exact rules come from the document you signed.

Two other terms come up often. A request for information (RFI) is a written question to the designer. Its answer may turn out to add work, which then becomes a change. A pending change order is a change that has been identified but not yet priced or signed. Many companies keep a pending change log, so nothing gets lost between the field and the office.

Where Changes Come From

Source Example
Owner request The owner adds an outlet, a wall or an upgraded finish
Design error or omission The drawings show a beam that does not fit, or leave out a detail
Hidden or differing conditions Rotted framing behind siding, rock in an excavation, an unmarked pipe
Code or inspector requirement The inspector requires work the drawings did not show
Answer to a question The RFI answer adds blocking that was not shown
Schedule change The owner asks you to finish early or work out of sequence

Is It a Change?

Compare what you are being asked to do with the contract documents: the drawings, specs, scope of work and any agreed changes so far. If it is not in them, it may be a change.

Request Likely a change?
Install the 14 doors on the door schedule No, it is base scope
Install a 15th door the owner just added Yes
Move a wall 2 feet after it has been framed Yes
Fix your own crew's framing that failed inspection No, that is your rework
Fix damage another trade caused to your finished work Maybe, through a backcharge to that trade, per the subcontract
Upgrade drywall to Type X because the inspector cited a fire-rated wall the drawings missed Yes, likely a design omission
Work overtime because your crew is behind No, unless the delay was caused by others

When you cannot tell, treat it as a possible change and ask. It is easy to drop a possible change later. It is hard to recover one nobody tracked.

What to Do When You Spot a Change

  1. Stop before you build it, unless waiting would create a safety hazard or damage. In an emergency, make it safe, and then notify.
  2. Tell your superintendent or project manager right away. Say what, where, who asked and why it looks like a change.
  3. Give written notice the way your contract requires. Many contracts set a deadline, counted in days from when you knew of the change, and some say a late notice can lose the right to be paid. The contract governs, so your project manager should tell you the deadline before the job starts.
  4. Document it. Photos, a daily report entry, the RFI or direction that caused it, and the names of people involved.
  5. Wait for written direction before you start, from a person with authority to give it. That might be a signed change order, a directive to proceed while the price is worked out, or an answer from your own company to proceed at its risk.
  6. Track the cost from the first minute if you proceed before a price is agreed.

Hidden Conditions

When you uncover something nobody could see at bid time, such as rot, rock, old wiring or a buried tank, do not disturb it further if you can avoid it. Make the area safe, photograph it wide, medium and close with a tape for scale, and notify in writing. Many contracts require prompt notice of a differing condition before it is disturbed, so the owner's side can look at it. If what you find could be asbestos, lead, a fuel tank or live utilities, stop and follow your company's procedure, because those have their own legal rules.

Working on Time and Material

Sometimes the work must go ahead before the price is agreed. The owner issues a directive, and the cost is settled later, often from time and material (T&M) tickets. A T&M ticket is a daily record of the labor, material and equipment spent on that extra work.

A ticket holds up when it:

  • Is written every day the work happens, not at the end.
  • Names the change, such as its pending change number or the directive.
  • Lists each worker, their trade or classification and their hours.
  • Lists material with quantities, and keeps the receipts or delivery tickets.
  • Lists equipment with hours used.
  • Describes the work and its location.
  • Is signed the same day by the owner's or general contractor's authorized representative. A signature shows the hours were seen, even if the rate is argued later.

Keep the T&M crew separate from the base contract work, so hours do not blur together. If a worker spends half a day on each, split the hours on the ticket and in your daily report.

How a Change Gets Priced

Your project manager prices the change, but the numbers come from the field. A change usually includes:

  • Labor: hours by trade, at the rates the contract allows.
  • Material: quantities and cost, including tax and delivery.
  • Equipment: rental or company equipment hours.
  • Subcontractors: their prices for their part.
  • Markup: overhead and profit, at the percentage the contract allows.
  • Time: extra working days, if the change affects the critical path.

Worked example. The owner adds a 12-foot interior wall with one door in a basement. These rates and the markup are made up for this example. Your contract sets the real ones.

  1. Labor. 2 carpenters x 6 hours = 12 hours. 12 x $68.00 = $816.00.
  2. Material. Studs, plates, door, hardware and fasteners from the takeoff: $420.00.
  3. Equipment. None.
  4. Subtotal. $816.00 + $420.00 = $1,236.00.
  5. Markup at 15 percent: $1,236.00 x 0.15 = $185.40.
  6. Carpentry total. $1,236.00 + $185.40 = $1,421.40.
  7. Other trades. Drywall, paint and an electrical switch are priced by those subcontractors and added in.
  8. Time. If the basement is on the critical path, ask for the day. If it has float, there may be no time impact.

Your part is the hours, the material list, and whether the crew had to stop or move other work to do it. Include the hidden costs: protecting finished work, extra cleanup, a second trip for an inspection, or a crew moved off a critical task.

Do Not Forget the Time

Many contracts treat a signed change order as the full settlement for that change, including any extra time. If a change pushes the schedule, raise the time before the change order is signed. Tell your project manager how many working days it affects and why, using the schedule. Once it is signed without time, it may be too late.

When the Owner Asks You in the Field

The owner is friendly, the request is small, and saying no feels rude. Say yes to the conversation and no to the commitment.

  1. Listen and take notes: what, where and why.
  2. Say: "I can't approve changes myself. I'll get this to my project manager today so it gets priced and done right."
  3. Do not give a price or a date on the spot, even a rough one. A guess in the field becomes a promise.
  4. Write it in your daily report and send it up the line the same day.

The same goes for other trades asking your crew to move or add work for them. Route it through your superintendent, who decides whether it is a change, a backcharge or a favor your company chooses to do.

Common Mistakes

Mistake What it costs Better habit
Doing extra work without notice It may never be paid Notify in writing before you build it
Missing the notice deadline Rights to payment or time can be lost Know the contract's deadline from day one
T&M tickets written at week's end Disputed hours Write and sign them daily
Mixing T&M hours with base work Neither can be proven Track them separately
Pricing in the field A guess becomes a promise Send every price question up the line
Signing off without time Delay you cannot recover Raise the schedule impact before signing
Disturbing a hidden condition Lost proof of what was there Make it safe, photograph, notify

Check Your Understanding

1. The architect answers an RFI by adding blocking for grab bars in 20 bathrooms that the drawings did not show. Is it a change, and what do you do?

Likely yes, because the work was not in the contract documents. Tell your project manager, give written notice as the contract requires, and track the cost once you are told to proceed.

2. Your crew is told to proceed with a change while the price is negotiated. What records do you keep?

A daily T&M ticket listing each worker, classification and hours, the material and equipment, the work and location, signed the same day by the authorized representative, plus a daily report entry.

3. The owner asks for an added closet and wants a price before she leaves. What do you say?

That you cannot approve or price changes yourself, and that you will get it to the project manager today. Then write it down and send it.

4. Demolition uncovers a buried fuel tank. What do you do first?

Stop work in the area, keep people back, and follow your company's procedure for that hazard. Then photograph and notify in writing. Do not dig it out yourself.

5. A change adds 3 working days to the critical path, but the draft change order shows only a price. What do you do?

Tell your project manager before it is signed, with the 3 days and the schedule logic behind them. Many contracts treat a signed change order as a full settlement.

Key Takeaways

  • A change order is a written change to the contract's work, price or time.
  • The contract decides who may approve a change and how fast you must give notice.
  • Stop, notify in writing and wait for written direction before building a change.
  • Track extra work on daily, signed T&M tickets, separate from base work.
  • Give your project manager the hours, material, equipment and time impact.
  • Never agree to a change or a price in the field.