Forming and Rebar: First Day on a Concrete Crew
See what a new helper does on a forming and rebar crew, learn the basic words and tools, and know what can hurt you on day one.
Table of contents
Concrete crews build the parts of a job that everything else stands on: footings, foundation walls, columns, slabs and sometimes whole structures. On a first day, you carry a lot, tie a lot of wire, and learn by watching. The work is hard and repetitive. It is also a trade that rewards anyone who pays attention, because a careful helper who learns forms and bars quickly stands out.
Before the concrete arrives, two jobs have to be done. Form carpenters build the molds that hold the concrete. Rodbusters, also called rebar workers or ironworkers on some jobs, place the steel that goes inside. A smaller crew may do both.
What You Will Be Able to Do
- Describe what a new helper does on a concrete crew.
- Name the basic forming and rebar parts and tools.
- Explain why forms are so heavily tied and braced.
- Name the hazards most likely to hurt you on your first day.
- Know what to bring, and what to ask.
What the Work Looks Like
Your first days will probably include:
- Moving material. Carrying form panels, ties, stakes and rebar to the crew.
- Setting and oiling forms. Holding panels while others pin or nail them, and applying release agent.
- Tying rebar. Twisting wire at bar intersections until your wrists get used to it.
- Stripping. Taking forms off cured concrete, cleaning them and stacking them.
- Helping on the pour. Moving hoses, raking concrete and cleaning tools.
- Cleaning up. Picking up ties, wire, nails and offcuts all day.
Crews work to schedules set by the concrete deliveries. When the trucks are coming, everyone moves fast. Your job is to keep tools and material where they are needed.
Words You Will Hear
| Word | Meaning |
|---|---|
| Form | The mold that holds concrete |
| Plyform | Plywood made for forms |
| Stud and waler | Vertical and horizontal backing on a form |
| Form tie | A steel tie that holds the two sides of a form together |
| Strip | Take forms off |
| Rebar | Steel reinforcing bar |
| Lap | Where two bars overlap |
| Cover | Concrete between the bar and the surface |
| Chair | A support that holds rebar at the right height |
| Pour | Placing concrete |
How Forms Work
Wet concrete behaves like a heavy liquid, and it pushes outward hard. Pressure is greatest at the bottom of the form, and it goes up if the pour is faster or the weather is colder. That is why forms have so many ties and braces, and why bracing comes from a plan rather than a guess. If you see a form bulging or a tie letting go during a pour, yell and get clear.
Forms come in a few types. Job-built forms use plywood and lumber, and handset forms are metal panels pinned together. Aluminum forms are common for house foundations. Insulated concrete forms are foam blocks that stay in the wall.
Forms come off in order, and only when the foreman says so. Side forms on a wall usually come off within a day or two. Shoring under a slab or beam stays much longer, often a week or more, and only the plans or a strength test can release it. Never pull a shore on your own.
How Rebar Works
Concrete resists crushing but cracks when pulled. Steel takes the pulling. Because of that, the location of each bar matters.
A few basics will take you a long way:
- Bar numbers give the diameter in eighths of an inch. A #4 bar is 1/2 inch, and a #5 is 5/8 inch.
- Grade 60 is the usual bar strength.
- Bars sit on chairs or bolsters so that concrete can get under them. A common cover is 3 inches where concrete sits against dirt.
- Laps are often about 40 bar diameters, but the drawing has the final word.
- Intersections are tied with 16-gauge wire. Ties hold bars in place until the concrete does.
Tools to Bring
Check with your foreman first. A helper often needs:
- Hammer and tape measure
- Lineman's or rebar pliers
- Tie wire reel and belt
- Utility knife and pencil
- Leather gloves
- Rubber boots for pour days
- Waterproof gloves for wet concrete
The crew usually supplies saws, levels, lasers, vibrators, pumps and tying tools.
What Can Hurt You on Day One
Wet Concrete
Warning: Wet concrete is strongly alkaline and can give you chemical burns, sometimes without much pain until later. Wear rubber boots, waterproof gloves, long sleeves and eye protection. Keep concrete out of your boots. If it touches your skin, wash with clean water right away. Change out of soaked clothing.
Exposed Rebar
OSHA 1926.701(b) requires that bars you could fall on be guarded so they cannot impale you. Small plastic mushroom caps are for scratches. They are not rated to stop impalement. Rated covers, wood troughs and bent-over bars can do the job. Look around before you walk, and never leave exposed bars unguarded near a ladder, walkway or edge.
Falls
Crews work on top of walls, at slab edges and in excavations. Fall protection is required at 6 feet or more in most construction work. Do not climb forms or ties, and do not walk the top of a wall form unless it has a proper platform.
Struck-By Hazards
Panels, bundles of bars and concrete buckets may be lifted over your work. Stay out from under loads. Pump hoses can whip. Trucks back up with little warning, so stand where drivers can see you.
Strains and Cuts
Bars are long and heavy, and tying is hard on backs and wrists. Lift with a partner, and change position often. Wire ends and bars can cut you. Wear gloves and long sleeves even in summer.
Good First-Day Habits
- Show up early, dressed for dirty work, with a lunch and plenty of water.
- Learn the name of the foreman and ask where the eyewash and first-aid kit are.
- Watch how journeymen set a panel or tie a bar before you try it.
- Ask where scrap ties, wire and rebar go.
- Keep your phone away from the work.
- Ask if you do not understand an order.
Your First Exercise
Watch a video of a residential footing or foundation wall being formed and poured. Note how the rebar is tied, where the chairs sit, how the forms are braced and how the crew moves as the truck arrives. On your first day, ask the foreman to walk you through that day's work and how forms will be stripped.
Check Your Understanding
1. While oiling forms, you see a wall form with several ties that look loose, and the pump is about to start. What do you do?
Tell the foreman right away. Ties hold the form against the concrete's pressure. A missing or loose tie can lead to a blowout.
2. You splash wet concrete on your forearm. What do you do?
Rinse it with clean water right away, and tell someone if your skin stings or looks red. Wash it even if it does not hurt yet.
3. A helper tells you that small plastic caps are enough to stop impalement on a rebar curtain. Are they?
No. Those caps protect against scrapes. Impalement needs rated covers, troughs or bending the bars over.
4. You are ready to pull a shore because the concrete looks hard. Should you?
No. Only the foreman, using the plans or strength test results, can release shores.
Key Takeaways
- A new helper carries, ties, oils and strips, and watches how experienced workers do it.
- Forms hold back huge pressure, so ties and bracing are not optional.
- Rebar goes where the drawing says, on supports, with the right cover and laps.
- Protect your skin from wet concrete.
- Guard exposed bars, stay out from under loads, and never pull a shore or form on your own.